Providing and fixing stainless steel (SS-304 grade) friction hinges to the side/top hung uPVC windows, of approved quality, with necessary stainless steel screws etc. as per direction of Engineer-in-charge
- Item number
- 9.148.2
- Analysis basis
- 10 Nos
- Priced inputs
- 5
- Derived rate
- ₹422.55/ NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.148.2 (Providing and fixing stainless steel (SS-304 grade) friction hinges to the side/top hung uPVC windows, of approved quality, with necessary stainless steel screws etc. as per direction of Engineer-in-charge 250 x 19 x 1.9 mm) is derived from 5 priced inputs for 10 Nos and works out to ₹422.55 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8756 | MAT | Stainless steel friction hinge of size 250 mm x 19 x 1.9 mm for uPVC windows | each | 10 | 273.00 | 2,730.00 |
| 8647 | MAT | Stainless steel screws 30mm x4mm.Stainless steel screws 30 mm x4 mm | 100 Nos | 0.4 | 42.00 | 16.80 |
| 9977 | MAT | Carriage of materials | L.S. | 2.73 | 2.27 | 6.20 |
| 0112 | LAB | Carpenter 2nd class | day | 0.14 | 816.00 | 114.24 |
| 0114 | LAB | Beldar | day | 0.14 | 736.00 | 103.04 |
- TOTAL
- 2,970.28
- Add 1 % Water charges on “W”
- +29.70
- TOTAL
- 2,999.98
- Add GST on “X” (multiplying factor 0.2127)
- +638.10
- TOTAL
- 3,638.08
- Add 15% CPOH on “Y”
- +545.71
- TOTAL
- 4,183.79
- Add Cess @ 1% on “Z”
- +41.84
- Cost of 10 Nos
- 4,225.63
- Cost of 1 No
- 422.56
- SAY
- ₹422.55
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 688
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 688. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.