CPWD Analysis of Rates · Wood and PVC Work

Providing and Fixing factory made uPVC door frame, made of uPVC exturded sections, of size 65 mm x 55 mm with wall thickness 2.0 mm (± 0.2 mm), corners of the door frame to be mitred cut and jointed with plastic brackets and stainless steel screws, reinforcing hinge side vertical of the frames with PVC profile of Size 28 mm x 30 mm having wall thickness 2 mm (±0.2 mm), including providing & fixing 3 nos of 125 mm long stainless steel hinges to the frame, fixing the frame with jamb with required number & size of anchor dash fastners, all complete as per manufacturer’s specification and direction of Engineer-in-charge

Item number
9.143
Analysis basis
Details of cost for one door frame of 5 metre
Priced inputs
4
Derived rate
623.00 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.143 Providing and Fixing factory made uPVC door frame, made of uPVC exturded sections, of size 65 mm x 55 mm with wall thickness 2.0 mm (± 0.2 mm), corners of the door frame to be mitred cut and jointed with plastic brackets and stainless steel screws, reinforcing hinge side vertical of the frames with PVC profile of Size 28 mm x 30 mm having wall thickness 2 mm (±0.2 mm), including providing & fixing 3 nos of 125 mm long stainless steel hinges to the frame, fixing the frame with jamb with required number & size of anchor dash fastners, all complete as per manufacturer’s specification and direction of Engineer-in-charge — is derived from 4 priced inputs for one door and works out to ₹623.00 per metre after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
874565mm x 55mm x 2mm thick Factory made door frame of PVC extruded section in white,grey or wooden finish65 mm x 55 mm x 2 mm thick Factory made door frame of PVC extruded section in white, grey or wooden finishMaterialmetre5388.001,940.00
0156Carpenter (average)Labourday0.15857.00128.55
0114BeldarLabourday0.15736.00110.40
9999SundriesMaterialL.S.4.682.2710.62
TOTAL
2,189.57
Add 1 % Water charges on “W”
21.90
TOTAL
2,211.47
Add GST on “X” (multiplying factor 0.2127)
470.38
TOTAL
2,681.85
Add 15% CPOH on “Y”
402.28
TOTAL
3,084.13
Add Cess @ 1% on “Z”
30.84
Cost of 5 metres
3,114.97
Cost of 1 metre
622.99
Say
623.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 624. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.