Providing and fixing plain lining with necessary screws/nuts & bolts/ nails, including a coat of approved primer on one face, and fixed on wooden /steel frame work, complete as per direction of Engineer-incharge (Frame work shall be paid for separately)

12mm thick commercial ply conforming to IS : 1328 BWR type

Item number
9.140.1
Analysis basis
Details of cost for 10 sqm
Priced inputs
6
Derived rate
1,224.65 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.140.1 Providing and fixing plain lining with necessary screws/nuts & bolts/ nails, including a coat of approved primer on one face, and fixed on wooden /steel frame work, complete as per direction of Engineer-incharge (Frame work shall be paid for separately) 12mm thick commercial ply conforming to IS : 1328 BWR type — is derived from 6 priced inputs for 10 sqm and works out to ₹1,224.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Priming coat
CodeInputUnitQuantityRate (INR)Amount (INR)
241312 mm commercial plyMaterialsqm11527.005,797.00
Rate as per Item Number 13.85.1 of SH: FinishingRate as per item 13.85.1Sub-analysissqm1070.35703.50
9999Sundries and screws etc.MaterialL.S.40.12.2791.03
0156Carpenter (average)Labourday1.28857.001,096.96
0114BeldarLabourday1.43736.001,052.48
9988Sundries and carriageMaterialL.S.33.562.2776.18
TOTAL
8,817.15
Add 1 % Water charges on “W-A”
81.14
TOTAL
8,898.29
Add GST on “X-A” (multiplying factor 0.2127)
1,743.03
TOTAL
10,641.32
Add 15% CPOH on “Y-A”
1,490.67
TOTAL
12,131.99
Add Cess @ 1% on “Z-A”
114.28
Cost of 10 sqm
12,246.27
Cost of 1 sqm
1,224.63
Say
1,224.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 621. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works