Providing and fixing plain lining with necessary screws/nuts & bolts/ nails, including a coat of approved primer on one face, and fixed on wooden /steel frame work, complete as per direction of Engineer-incharge (Frame work shall be paid for separately)

12mm thick commercial ply conforming to IS : 1328 BWR type
Item number
9.140.1
Analysis basis
10 sqm
Priced inputs
6
Derived rate
₹1,224.65/ SQM
D-01/RATE ANALYSISITEM 9.140.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.140.1 (Providing and fixing plain lining with necessary screws/nuts & bolts/ nails, including a coat of approved primer on one face, and fixed on wooden /steel frame work, complete as per direction of Engineer-incharge (Frame work shall be paid for separately) 12mm thick commercial ply conforming to IS : 1328 BWR type) is derived from 6 priced inputs for 10 sqm and works out to ₹1,224.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Priming coat
ANALYSIS OF RATES · ITEM 9.140.1DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
2413MAT12 mm commercial plysqm11527.005,797.00
SUBRate as per Item Number 13.85.1 of SH: FinishingRate as per item 13.85.1sqm1070.35703.50
9999MATSundries and screws etc.L.S.40.12.2791.03
0156LABCarpenter (average)day1.28857.001,096.96
0114LABBeldarday1.43736.001,052.48
9988MATSundries and carriageL.S.33.562.2776.18
BUILD-UP TO RATE
TOTAL
8,817.15
Add 1 % Water charges on “W-A”
+81.14
TOTAL
8,898.29
Add GST on “X-A” (multiplying factor 0.2127)
+1,743.03
TOTAL
10,641.32
Add 15% CPOH on “Y-A”
+1,490.67
TOTAL
12,131.99
Add Cess @ 1% on “Z-A”
+114.28
Cost of 10 sqm
12,246.27
Cost of 1 sqm
1,224.63
SAY
₹1,224.65
D-02/SOURCEPRINTED PAGE 621
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
621

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 621. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.