Providing and fixing plain lining with necessary screws/nuts & bolts/ nails, including a coat of approved primer on one face, and fixed on wooden /steel frame work, complete as per direction of Engineer-incharge (Frame work shall be paid for separately)
- Item number
- 9.140.1
- Analysis basis
- 10 sqm
- Priced inputs
- 6
- Derived rate
- ₹1,224.65/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.140.1 (Providing and fixing plain lining with necessary screws/nuts & bolts/ nails, including a coat of approved primer on one face, and fixed on wooden /steel frame work, complete as per direction of Engineer-incharge (Frame work shall be paid for separately) 12mm thick commercial ply conforming to IS : 1328 BWR type) is derived from 6 priced inputs for 10 sqm and works out to ₹1,224.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Priming coat
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 2413 | MAT | 12 mm commercial ply | sqm | 11 | 527.00 | 5,797.00 |
| SUB | Rate as per Item Number 13.85.1 of SH: FinishingRate as per item 13.85.1 | sqm | 10 | 70.35 | 703.50 | |
| 9999 | MAT | Sundries and screws etc. | L.S. | 40.1 | 2.27 | 91.03 |
| 0156 | LAB | Carpenter (average) | day | 1.28 | 857.00 | 1,096.96 |
| 0114 | LAB | Beldar | day | 1.43 | 736.00 | 1,052.48 |
| 9988 | MAT | Sundries and carriage | L.S. | 33.56 | 2.27 | 76.18 |
- TOTAL
- 8,817.15
- Add 1 % Water charges on “W-A”
- +81.14
- TOTAL
- 8,898.29
- Add GST on “X-A” (multiplying factor 0.2127)
- +1,743.03
- TOTAL
- 10,641.32
- Add 15% CPOH on “Y-A”
- +1,490.67
- TOTAL
- 12,131.99
- Add Cess @ 1% on “Z-A”
- +114.28
- Cost of 10 sqm
- 12,246.27
- Cost of 1 sqm
- 1,224.63
- SAY
- ₹1,224.65
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 621
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 621. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.