CPWD Analysis of Rates · Wood and PVC Work
Providing and fixing fly proof stainless steel grade 304 wire gauge, to windows and clerestory windows using wire gauge with average width of aperture 1.4 mm in both directions with wire of dia. 0.50 mm all complete
With 2nd class teak wood beading 62X19 mm
- Item number
- 9.135.1
- Analysis basis
- Details of cost for a window of size 140x110cm
- Priced inputs
- 6
- Derived rate
- ₹1,597.15 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.135.1 — Providing and fixing fly proof stainless steel grade 304 wire gauge, to windows and clerestory windows using wire gauge with average width of aperture 1.4 mm in both directions with wire of dia. 0.50 mm all complete With 2nd class teak wood beading 62X19 mm — is derived from 6 priced inputs for a window and works out to ₹1,597.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- =1.54sqm.
- Wire gauze -20x60mm mesh 3.2mm
- wide = 1.4x1.1m = 1.54sqm.+
- Total = 1.69 sqm.
- Second class teak wood beading 5mx62mmx19mm = 0.0059cum.
- Total = 0.00649cum. Say 6 cudm.
- Add wastage @ 10% = 0.15sqm.
- Add wastage @ 10% = 0.00059cum.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8737 | Stainless steel wire guage (Grade-304) aperture 1.4mm and 0.50 mm dia wireStainless steel wire guage (Grade-304) aperture 1.4 mm and 0.50 mm dia wireMaterial | sqm | 1.69 | 445.00 | 752.05 |
| 9977 | Carriage of wire fabricMaterial | L.S. | 1.82 | 2.27 | 4.13 |
| 1190 | Second class teak wood in planksMaterial | 10 cudm | 0.6 | 791.00 | 474.60 |
| 0112 | Carpenter 2nd classLabour | day | 0.33 | 816.00 | 269.28 |
| 0114 | BeldarLabour | day | 0.25 | 736.00 | 184.00 |
| 9999 | SundriesMaterial | L.S. | 19.76 | 2.27 | 44.86 |
- TOTAL
- 1,728.92
- Add 1 % Water charges on “W”
- 17.29
- TOTAL
- 1,746.21
- Add GST on “X” (multiplying factor 0.2127)
- 371.42
- TOTAL
- 2,117.63
- Add 15% CPOH on “Y”
- 317.64
- TOTAL
- 2,435.27
- Add Cess @ 1% on “Z”
- 24.35
- Cost of 1.54 sqm.
- 2,459.62
- Cost of 1 sqm.
- 1,597.16
- Say
- 1,597.15
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 618. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.