Providing PVC moulding / architrave for door frame made up of extruded solid foam PVC profile having homogenous fine cellular structure with smooth outer integral skin, minimum 30 mm width and minimum 12 mm thick suitable for fixing to frame. The molding shall be snap fitted in the groove provided in the frame & fixed with PVC solvent adhesive / cement and self tapping screws (of required size) complete as per direction of Engineer-in-Charge

Item number
9.123A
Analysis basis
Details of cost for moulding/architrave (around
Priced inputs
4
Derived rate
135.80 / metre Door Frame

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.123A Providing PVC moulding / architrave for door frame made up of extruded solid foam PVC profile having homogenous fine cellular structure with smooth outer integral skin, minimum 30 mm width and minimum 12 mm thick suitable for fixing to frame. The molding shall be snap fitted in the groove provided in the frame & fixed with PVC solvent adhesive / cement and self tapping screws (of required size) complete as per direction of Engineer-in-Charge — is derived from 4 priced inputs and works out to ₹135.80 per metre door frame after water charges, GST, CPOH and cess. The full build-up is below.

  • door frame) 0.80 m x 2.1 m = 5 metre
  • Sundries for PVC solvent adhesive and self
  • tapping screws
  • labour for fixing
CodeInputUnitQuantityRate (INR)Amount (INR)
8235Factory made foam PVC moulded/extruded profile architrave of size 30 mm x 12mmFactory made foam PVC moulded/extruded profile architrave of size 30 mm x 12 mmMaterialmetre575.00375.00
9999SundriesMaterialL.S.102.2722.70
0156Carpenter (average)LabourDay0.05857.0042.85
0114BelderBeldarLabourDay0.05736.0036.80
TOTAL
477.35
Add 1 % Water charges on “W”
4.77
TOTAL
482.12
Add GST on “X” (multiplying factor 0.2127)
102.55
TOTAL
584.67
Add 15% CPOH on “Y”
87.70
TOTAL
672.37
Add Labour cess @ 1%
6.72
Cost of 5 metre
679.09
Cost of 1 metre Door Frame
135.82
say
135.80

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 595. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.