Providing PVC moulding / architrave for door frame made up of extruded solid foam PVC profile having homogenous fine cellular structure with smooth outer integral skin, minimum 30 mm width and minimum 12 mm thick suitable for fixing to frame. The molding shall be snap fitted in the groove provided in the frame & fixed with PVC solvent adhesive / cement and self tapping screws (of required size) complete as per direction of Engineer-in-Charge
- Item number
- 9.123A
- Analysis basis
- Details of cost for moulding/architrave (around
- Priced inputs
- 4
- Derived rate
- ₹135.80 / metre Door Frame
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.123A — Providing PVC moulding / architrave for door frame made up of extruded solid foam PVC profile having homogenous fine cellular structure with smooth outer integral skin, minimum 30 mm width and minimum 12 mm thick suitable for fixing to frame. The molding shall be snap fitted in the groove provided in the frame & fixed with PVC solvent adhesive / cement and self tapping screws (of required size) complete as per direction of Engineer-in-Charge — is derived from 4 priced inputs and works out to ₹135.80 per metre door frame after water charges, GST, CPOH and cess. The full build-up is below.
- door frame) 0.80 m x 2.1 m = 5 metre
- Sundries for PVC solvent adhesive and self
- tapping screws
- labour for fixing
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8235 | Factory made foam PVC moulded/extruded profile architrave of size 30 mm x 12mmFactory made foam PVC moulded/extruded profile architrave of size 30 mm x 12 mmMaterial | metre | 5 | 75.00 | 375.00 |
| 9999 | SundriesMaterial | L.S. | 10 | 2.27 | 22.70 |
| 0156 | Carpenter (average)Labour | Day | 0.05 | 857.00 | 42.85 |
| 0114 | BelderBeldarLabour | Day | 0.05 | 736.00 | 36.80 |
- TOTAL
- 477.35
- Add 1 % Water charges on “W”
- 4.77
- TOTAL
- 482.12
- Add GST on “X” (multiplying factor 0.2127)
- 102.55
- TOTAL
- 584.67
- Add 15% CPOH on “Y”
- 87.70
- TOTAL
- 672.37
- Add Labour cess @ 1%
- 6.72
- Cost of 5 metre
- 679.09
- Cost of 1 metre Door Frame
- 135.82
- say
- 135.80
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 595. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.