CPWD Analysis of Rates · Wood and PVC Work

Providing and fixing Fiber Glass Reinforced plastic (FRP) Door Frames of cross-section 90 mm x 45 mm having single rebate of 32 mm x 15 mm to receive shutter of 30 mm thickness. The laminate shall be moulded with fire resistant grade unsaturated polyester resin and chopped mat. Door frame laminate shall be 2mm thick and shall be filled with suitable wooden block in all the three legs. The frame shall be covered with fiber glass from all sides. M.S. stay shall be provided at the bottom to steady the frame

Item number
9.121
Analysis basis
Details of cost for one door frame of 5 metre
Priced inputs
4
Derived rate
570.95 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.121 Providing and fixing Fiber Glass Reinforced plastic (FRP) Door Frames of cross-section 90 mm x 45 mm having single rebate of 32 mm x 15 mm to receive shutter of 30 mm thickness. The laminate shall be moulded with fire resistant grade unsaturated polyester resin and chopped mat. Door frame laminate shall be 2mm thick and shall be filled with suitable wooden block in all the three legs. The frame shall be covered with fiber glass from all sides. M.S. stay shall be provided at the bottom to steady the frame — is derived from 4 priced inputs for one door and works out to ₹570.95 per metre after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
8707Factory made glass reinforced plastic door frame 90x45 mm i/c carriageMaterialmetre5350.001,750.00
0156Carpenter (average)Labourday0.15857.00128.55
0114BeldarLabourday0.15736.00110.40
9999SundriesMaterialL.S.7.82.2717.71
TOTAL
2,006.66
Add 1 % Water charges on “W”
20.07
TOTAL
2,026.73
Add GST on “X” (multiplying factor 0.2127)
431.09
TOTAL
2,457.82
Add 15% CPOH on “Y”
368.67
TOTAL
2,826.49
Add Cess @ 1% on “Z”
28.26
Cost of 5 metres
2,854.75
Cost of 1 metre
570.95
Say
570.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 592. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works