Skip to main content

CPWD Analysis of Rates · Wood and PVC Work

Providing and fixing factory made P.V.C. door frame of size 50x47 mm with a wall thickness of 5 mm, made out of extruded 5mm rigid PVC foam sheet, mitred at corners and joined with 2 Nos of 150 mm long brackets of 15x15 mm M.S. square tube, the vertical door frame profiles to be reinforced with 19x19 mm M.S. square tube of 19 gauge, EPDM rubber gasket weather seal to be provided through out the frame. The door frame to be fixed to the wall using M.S. screws of 65/100 mm size, complete as per manufacturer’s specification and direction of Engineerin-Charge

Item number
9.119
Analysis basis
Details of cost for one door frame of 5 metre
Priced inputs
4
Derived rate
492.70 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.119 Providing and fixing factory made P.V.C. door frame of size 50x47 mm with a wall thickness of 5 mm, made out of extruded 5mm rigid PVC foam sheet, mitred at corners and joined with 2 Nos of 150 mm long brackets of 15x15 mm M.S. square tube, the vertical door frame profiles to be reinforced with 19x19 mm M.S. square tube of 19 gauge, EPDM rubber gasket weather seal to be provided through out the frame. The door frame to be fixed to the wall using M.S. screws of 65/100 mm size, complete as per manufacturer’s specification and direction of Engineerin-Charge — is derived from 4 priced inputs for one door and works out to ₹492.70 per metre after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
8011Factory made 50mmx47mm with a wall thickness of 5mm door frame PVC extruded sheet i/c carriageFactory made 50 mmx47 mm with a wall thickness of 5 mm door frame PVC extruded sheet i/c carriageMaterialmetre5295.001,475.00
0156Carpenter (average)Labourday0.15857.00128.55
0114BeldarLabourday0.15736.00110.40
9999SundriesMaterialL.S.7.82.2717.71
TOTAL
1,731.66
Add 1 % Water charges on “W”
17.32
TOTAL
1,748.98
Add GST on “X” (multiplying factor 0.2127)
372.01
TOTAL
2,120.99
Add 15% CPOH on “Y”
318.15
TOTAL
2,439.14
Add Cess @ 1% on “Z”
24.39
Cost of 5 metres
2,463.53
Cost of 1 metre
492.71
Say
492.70

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 590. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works