Providing and fixing magnetic catcher of approved quality in cupboard / ward robe shutters, including fixing with necessary screws etc. complete

Triple strip vertical type
Item number
9.114.1
Analysis basis
1 no
Priced inputs
2
Derived rate
₹52.50/ NO
D-01/RATE ANALYSISITEM 9.114.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.114.1 (Providing and fixing magnetic catcher of approved quality in cupboard / ward robe shutters, including fixing with necessary screws etc. complete Triple strip vertical type) is derived from 2 priced inputs for 1 no and works out to ₹52.50 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.114.1DETAILS OF COST FOR 1 NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8714MATMagenatic catcher triple strip verticle type.Magnetic catcher triple strip vertical typeeach131.0031.00
9999MATSundries including screws and fixing charges.L.S.2.62.275.90
BUILD-UP TO RATE
TOTAL
36.90
Add 1 % Water charges on “W”
+0.37
TOTAL
37.27
Add GST on “X” (multiplying factor 0.2127)
+7.93
TOTAL
45.20
Add 15% CPOH on “Y”
+6.78
TOTAL
51.98
Add Cess @ 1% on “Z”
+0.52
Cost for 1 No.
52.50
SAY
₹52.50
D-02/SOURCEPRINTED PAGE 585
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
585

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 585. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.