Providing and fixing 2nd class teak wood lipping/ moulded beading or taj beading of size 18X5 mm fixed with wooden adhesive of approved quality and screws/nails on the edges of the Prelaminated particle board as per direction of Engineer-in-charge

Item number
9.112
Analysis basis
10.00 m
Priced inputs
3
Derived rate
₹102.15/ M
D-01/RATE ANALYSISITEM 9.112

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.112 (Providing and fixing 2nd class teak wood lipping/ moulded beading or taj beading of size 18X5 mm fixed with wooden adhesive of approved quality and screws/nails on the edges of the Prelaminated particle board as per direction of Engineer-in-charge) is derived from 3 priced inputs for 10.00 m and works out to ₹102.15 per m after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.112DETAILS OF COST FOR 10.00 M
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8719MAT2nd class teak wood lipping/ moulded beadibg or Taj beading of size 18X5mm2nd class teak wood moulded beading or Taj beading/ornamental beading of size 18X5 mmmetre1033.00330.00
0112LABCarpenter 2nd classday0.25816.00204.00
0114LABBeldarday0.25736.00184.00
BUILD-UP TO RATE
TOTAL
718.00
Add 1 % Water charges on “W”
+7.18
TOTAL
725.18
Add GST on “X” (multiplying factor 0.2127)
+154.25
TOTAL
879.43
Add 15% CPOH on “Y”
+131.91
TOTAL
1,011.34
Add Cess @ 1% on “Z”
+10.11
Cost for 10 metre
1,021.45
Cost for 1 metre
102.15
SAY
₹102.15
D-02/SOURCEPRINTED PAGE 585
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
585

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 585. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.