CPWD Analysis of Rates · Wood and PVC Work

Extra for providing heavy sheet float glass panes instead of ordinary float glass in glazed doors, windows and clerestory window shutters. (Area of opening for glass panes excluding portion inside rebate shall be measured)

5.0 mm thick (weight not less than 12.50 kg per sqm) instead of 4 mm thick (weight not less than 10 kg per sqm)

Item number
9.11.1
Analysis basis
Details of cost for one sqm.
Priced inputs
2
Derived rate
295.90 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.11.1 Extra for providing heavy sheet float glass panes instead of ordinary float glass in glazed doors, windows and clerestory window shutters. (Area of opening for glass panes excluding portion inside rebate shall be measured) 5.0 mm thick (weight not less than 12.50 kg per sqm) instead of 4 mm thick (weight not less than 10 kg per sqm) — is derived from 2 priced inputs for one sqm and works out to ₹295.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Deduct
CodeInputUnitQuantityRate (INR)Amount (INR)
2407Float glass sheet of nominal thickness 5.0 mm.(weight not less than 12.50 kg/sqm)Float glass panes of nominal thickness 5 mm (weight not less than 12.50 kg/sqm)Materialsqm1529.00529.00
2406Float glass sheet of nominal thickness 4 mm (weight not less than 10kg/sqm)Float glass panes of nominal thickness 4 mm (weight not less than 10 kg/sqm)Materialsqm-1321.00-321.00
TOTAL
208.00
Add 1 % Water charges on “W”
2.08
TOTAL
210.08
Add GST on “X” (multiplying factor 0.2127)
44.68
TOTAL
254.76
Add 15% CPOH on “Y”
38.21
TOTAL
292.97
Add Cess @ 1% on “Z”
2.93
Cost of 1 sqm.
295.90
Say
295.90

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 463. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.