CPWD Analysis of Rates · Wood and PVC Work

Providing and fixing factory made laminated veneer lumber glazed shutter conforming to IS: 14616 and TADS 15:2001 (Part B), using 4 mm thick float glass panes for doors, windows and clerestory windows, fixing with butt hinges of required size with necessary screws, all as per directions of Engineer-in-charge (Note:- Butt hinges and necessary screws shall be paid separately)

30 mm thick shutters

Item number
9.10.1
Analysis basis
Details of cost of one shutter
Priced inputs
5
Derived rate
3,066.20 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.10.1 Providing and fixing factory made laminated veneer lumber glazed shutter conforming to IS: 14616 and TADS 15:2001 (Part B), using 4 mm thick float glass panes for doors, windows and clerestory windows, fixing with butt hinges of required size with necessary screws, all as per directions of Engineer-in-charge (Note:- Butt hinges and necessary screws shall be paid separately) 30 mm thick shutters — is derived from 5 priced inputs and works out to ₹3,066.20 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • 220x108cm = 2.38sqm.
CodeInputUnitQuantityRate (INR)Amount (INR)
7151Factory made 30 mm thick shutters with laminated veneer lumber styles rails as per TADS IS:1995 and panels of sheet glass using 10 kg/ sqm glass panesFactory made 30 mm thick shutters with laminated veneer lumber styles & rails as per TADS 15:1995 and panels of sheet glass using 10 kg/ sqm glass panesMaterialsqm2.381,720.004,093.60
9977Carriage of shuttersMaterialL.S.29.642.2767.28
0156Carpenter (average)Labourday0.52857.00445.64
0114BeldarLabourday0.6736.00441.60
9999SundriesMaterialL.S.35.882.2781.45
TOTAL
5,129.57
Add 1 % Water charges on “W”
51.30
TOTAL
5,180.87
Add GST on “X” (multiplying factor 0.2127)
1,101.97
TOTAL
6,282.84
Add 15% CPOH on “Y”
942.43
TOTAL
7,225.27
Add Cess @ 1% on “Z”
72.25
Cost of 2.38 sqm.
7,297.52
Cost of 1 sqm.
3,066.18
Say
3,066.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 462. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.