Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply including all CPVC plain & brass threaded fittings This includes jointing of pipes & fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge. External work

65 mm nominal dia Pipes
Item number
18.9.7
Analysis basis
10 metre
Priced inputs
5
Derived rate
₹1,674.40/ METRE
D-01/RATE ANALYSISITEM 18.9.7

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.9.7 (Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply including all CPVC plain & brass threaded fittings This includes jointing of pipes & fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge. External work 65 mm nominal dia Pipes) is derived from 5 priced inputs for 10 metre and works out to ₹1,674.40 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 30 x P / 100
  • Trenching and refilling etc.
ANALYSIS OF RATES · ITEM 18.9.7DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8642MATChlorinated Polyvinyl - chloride (CPVC) pipe 65 mm nominal diametre10776.007,760.00
0116LABFitter (grade 1)day0.25897.00224.25
0114LABBeldarday0.66736.00485.76
0114LABBeldarday0.66736.00485.76
0115LABCoolieday0.66736.00485.76
BUILD-UP TO RATE
Add 30% for fittings and wastage etc. on (P)
+2,328.00
TOTAL
11,769.53
Add 1 % Water charges on “W”
+117.70
TOTAL
11,887.23
Add GST on “X” (multiplying factor 0.2127)
+2,528.41
TOTAL
14,415.64
Add 15% CPOH on “Y”
+2,162.35
TOTAL
16,577.99
Add Cess @ 1% on “Z”
+165.78
Cost of 10 metre
16,743.77
Cost of 1 metre
1,674.38
SAY
₹1,674.40
D-02/SOURCEPRINTED PAGE 1424
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1424

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1424. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.