Skip to main content
R/DAR 2023

Providing and fixing Stainless Steel pipe and fitting of grade 316L as per IS 6911:2017 and conforming to EN-10312 standards complete with press type fitting (fitting shall be paid for separately) i/c fixing of the pipe with clamps at 1.00 m spacing including cutting and making good the walls including testing of joints complete as per direction of Engineer-in-charge. (The pipe length inserted in the fitting shall not be measured for payment) Internal work - Exposed on wall

42 mm outer dia Pipe
Item number
18.85A.5
Analysis basis
10 metre
Priced inputs
5
Derived rate
₹2,124.00/ METRE
D-01/RATE ANALYSISITEM 18.85A.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.85A.5 (Providing and fixing Stainless Steel pipe and fitting of grade 316L as per IS 6911:2017 and conforming to EN-10312 standards complete with press type fitting (fitting shall be paid for separately) i/c fixing of the pipe with clamps at 1.00 m spacing including cutting and making good the walls including testing of joints complete as per direction of Engineer-in-charge. (The pipe length inserted in the fitting shall not be measured for payment) Internal work - Exposed on wall 42 mm outer dia Pipe) is derived from 5 priced inputs for 10 metre and works out to ₹2,124.00 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 3xP/ 100
  • 2xP/ 100
ANALYSIS OF RATES · ITEM 18.85A.5DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
3866MATSS pipe 316L grade as per IS 6911:2017 with press fit technology conforming to EN-10312 standards 42 mm outer diaSS pipe 316L grade as per IS 6911:2017 with press fit technology and conforming to EN-10312 standard 42 mm outer diametre101,295.0012,950.00
9999MATCement, sand and gritL.S.5.332.2712.10
0116LABFitter (grade 1)day0.33897.00296.01
0117LABAssistant Fitter or 2nd class Fitterday0.66816.00538.56
0114LABBeldarday0.66736.00485.76
BUILD-UP TO RATE
Add 3% for pipe inserted into fitting and wastage etc. on P
+388.50
Add 2% for special T&P and sundries etc. on P
+259.00
TOTAL
14,929.93
Add 1 % Water charges on “W”
+149.30
TOTAL
15,079.23
Add GST on “X” (multiplying factor 0.2127)
+3,207.35
TOTAL
18,286.58
Add 15% CPOH on “Y”
+2,742.99
TOTAL
21,029.57
Add Cess @ 1% on “Z”
+210.30
Cost of 10 metre
21,239.87
Cost of 1 metre
2,123.99
SAY
₹2,124.00
D-02/SOURCEPRINTED PAGE 1596
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1596

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1596. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.