Providing and fixing Stainless Steel pipe and fitting of grade 316L as per IS 6911:2017 and conforming to EN-10312 standards complete with press type fitting (fitting shall be paid for separately) i/c fixing of the pipe with clamps at 1.00 m spacing including cutting and making good the walls including testing of joints complete as per direction of Engineer-in-charge. (The pipe length inserted in the fitting shall not be measured for payment) Internal work - Exposed on wall
- Item number
- 18.85A.4
- Analysis basis
- 10 metre
- Priced inputs
- 5
- Derived rate
- ₹1,765.10/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.85A.4 (Providing and fixing Stainless Steel pipe and fitting of grade 316L as per IS 6911:2017 and conforming to EN-10312 standards complete with press type fitting (fitting shall be paid for separately) i/c fixing of the pipe with clamps at 1.00 m spacing including cutting and making good the walls including testing of joints complete as per direction of Engineer-in-charge. (The pipe length inserted in the fitting shall not be measured for payment) Internal work - Exposed on wall 35 mm outer dia Pipe) is derived from 5 priced inputs for 10 metre and works out to ₹1,765.10 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- 3xP/ 100
- 2xP/ 100
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 3865 | MAT | SS pipe 316L grade as per IS 6911:2017 with press fit technology conforming to EN-10312 standards 35 mm outer diaSS pipe 316L grade as per IS 6911:2017 with press fit technology and conforming to EN-10312 standard 35 mm outer dia | metre | 10 | 1,055.00 | 10,550.00 |
| 9999 | MAT | Cement, sand and grit | L.S. | 4.16 | 2.27 | 9.44 |
| 0116 | LAB | Fitter (grade 1) | day | 0.33 | 897.00 | 296.01 |
| 0117 | LAB | Assistant Fitter or 2nd class Fitter | day | 0.66 | 816.00 | 538.56 |
| 0114 | LAB | Beldar | day | 0.66 | 736.00 | 485.76 |
- Add 3% for pipe inserted into fitting and wastage etc. on P
- +316.50
- Add 2% for special T&P and sundries etc. on P
- +211.00
- TOTAL
- 12,407.27
- Add 1 % Water charges on “W”
- +124.07
- TOTAL
- 12,531.34
- Add GST on “X” (multiplying factor 0.2127)
- +2,665.42
- TOTAL
- 15,196.76
- Add 15% CPOH on “Y”
- +2,279.51
- TOTAL
- 17,476.27
- Add Cess @ 1% on “Z”
- +174.76
- Cost of 10 metre
- 17,651.03
- Cost of 1 metre
- 1,765.10
- SAY
- ₹1,765.10
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1596
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1596. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.