CPWD Analysis of Rates · Water Supply

Providing and fixing Stainless Steel pipe and fitting of grade 316L as per IS 6911:2017 and conforming to EN-10312 standards complete with press type fitting (fitting shall be paid for separately) i/c fixing of the pipe with clamps at 1.00 m spacing including cutting and making good the walls including testing of joints complete as per direction of Engineer-in-charge. (The pipe length inserted in the fitting shall not be measured for payment) Internal work - Exposed on wall

35 mm outer dia Pipe

Item number
18.85A.4
Analysis basis
Details of cost for 10 metre
Priced inputs
5
Derived rate
1,765.10 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.85A.4 Providing and fixing Stainless Steel pipe and fitting of grade 316L as per IS 6911:2017 and conforming to EN-10312 standards complete with press type fitting (fitting shall be paid for separately) i/c fixing of the pipe with clamps at 1.00 m spacing including cutting and making good the walls including testing of joints complete as per direction of Engineer-in-charge. (The pipe length inserted in the fitting shall not be measured for payment) Internal work - Exposed on wall 35 mm outer dia Pipe — is derived from 5 priced inputs for 10 metre and works out to ₹1,765.10 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • 3xP/ 100
  • 2xP/ 100
CodeInputUnitQuantityRate (INR)Amount (INR)
3865SS pipe 316L grade as per IS 6911:2017 with press fit technology conforming to EN-10312 standards 35 mm outer diaSS pipe 316L grade as per IS 6911:2017 with press fit technology and conforming to EN-10312 standard 35 mm outer diaMaterialmetre101,055.0010,550.00
9999Cement, sand and gritMaterialL.S.4.162.279.44
0116Fitter (grade 1)Labourday0.33897.00296.01
0117Assistant Fitter or 2nd class FitterLabourday0.66816.00538.56
0114BeldarLabourday0.66736.00485.76
Add 3% for pipe inserted into fitting and wastage etc. on P
316.50
Add 2% for special T&P and sundries etc. on P
211.00
TOTAL
12,407.27
Add 1 % Water charges on “W”
124.07
TOTAL
12,531.34
Add GST on “X” (multiplying factor 0.2127)
2,665.42
TOTAL
15,196.76
Add 15% CPOH on “Y”
2,279.51
TOTAL
17,476.27
Add Cess @ 1% on “Z”
174.76
Cost of 10 metre
17,651.03
Cost of 1 metre
1,765.10
Say
1,765.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1596. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.