Providing and fixing Stainless Steel pipe and fitting of grade AISI 304 as per JIS standard 3448 complete with press type fitting (fitting shall be paid for separately) i/c fixing of the pipe with clamps at 1.00 m spacing including cutting and making good the walls including testing of joints complete as per direction of Engineer-in-charge. (The pipe length inserted in the fitting shall not be measured for payment) Internal work - Exposed on wall
28.58 mm outer dia Pipe
- Item number
- 18.85.3
- Analysis basis
- Details of cost for 10 metre
- Priced inputs
- 5
- Derived rate
- ₹704.55 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.85.3 — Providing and fixing Stainless Steel pipe and fitting of grade AISI 304 as per JIS standard 3448 complete with press type fitting (fitting shall be paid for separately) i/c fixing of the pipe with clamps at 1.00 m spacing including cutting and making good the walls including testing of joints complete as per direction of Engineer-in-charge. (The pipe length inserted in the fitting shall not be measured for payment) Internal work - Exposed on wall 28.58 mm outer dia Pipe — is derived from 5 priced inputs for 10 metre and works out to ₹704.55 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- 3 xP/ 100
- 2xP/ 100
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8781 | SS pipe 304 grades with press fit technology as per JIS 3448 standard 28.58 mm outer diaMaterial | metre | 10 | 345.00 | 3,450.00 |
| 9999 | Cement, sand and gritMaterial | L.S. | 4.16 | 2.27 | 9.44 |
| 0116 | Fitter (grade 1)Labour | day | 0.33 | 897.00 | 296.01 |
| 0117 | Assistant Fitter or 2nd class FitterLabour | day | 0.66 | 816.00 | 538.56 |
| 0114 | BeldarLabour | day | 0.66 | 736.00 | 485.76 |
- Add 3% for pipe inserted into fitting and wastage etc. on P
- 103.50
- Add 2% for special T&P and sundries etc. on P
- 69.00
- TOTAL
- 4,952.27
- Add 1 % Water charges on “W”
- 49.52
- TOTAL
- 5,001.79
- Add GST on “X” (multiplying factor 0.2127)
- 1,063.88
- TOTAL
- 6,065.67
- Add 15% CPOH on “Y”
- 909.85
- TOTAL
- 6,975.52
- Add Cess @ 1% on “Z”
- 69.76
- Cost of 10 metre
- 7,045.28
- Cost of 1 metre
- 704.53
- Say
- 704.55
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1592. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.