Skip to main content
R/DAR 2023

Labour for cutting C.I. pipe with steel saw

350 mm diameter C.I. pipe
Item number
18.83.8
Analysis basis
one cut
Priced inputs
3
Derived rate
₹847.95/ ONE CUT
D-01/RATE ANALYSISITEM 18.83.8

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.83.8 (Labour for cutting C.I. pipe with steel saw 350 mm diameter C.I. pipe) is derived from 3 priced inputs for one cut and works out to ₹847.95 per one cut after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 18.83.8DETAIL OF COST FOR ONE CUT
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0116LABFitter (grade 1)day0.35897.00313.95
0114LABBeldarday0.35736.00257.60
9999MATSundriesL.S.10.792.2724.49
BUILD-UP TO RATE
TOTAL
596.04
Add 1 % Water charges on “W”
+5.96
TOTAL
602.00
Add GST on “X” (multiplying factor 0.2127)
+128.05
TOTAL
730.05
Add 15% CPOH on “Y”
+109.51
TOTAL
839.56
Add Cess @ 1% on “Z”
+8.40
Cost of each cut
847.96
SAY
₹847.95
D-02/SOURCEPRINTED PAGE 1589
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1589

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1589. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.