Skip to main content
R/DAR 2023

Labour for cutting C.I. pipe with steel saw

300 mm diameter C.I. pipe
Item number
18.83.7
Analysis basis
one cut
Priced inputs
3
Derived rate
₹728.85/ ONE CUT
D-01/RATE ANALYSISITEM 18.83.7

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.83.7 (Labour for cutting C.I. pipe with steel saw 300 mm diameter C.I. pipe) is derived from 3 priced inputs for one cut and works out to ₹728.85 per one cut after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 18.83.7DETAIL OF COST FOR ONE CUT
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0116LABFitter (grade 1)day0.3897.00269.10
0114LABBeldarday0.3736.00220.80
9999MATSundriesL.S.9.882.2722.43
BUILD-UP TO RATE
TOTAL
512.33
Add 1 % Water charges on “W”
+5.12
TOTAL
517.45
Add GST on “X” (multiplying factor 0.2127)
+110.06
TOTAL
627.51
Add 15% CPOH on “Y”
+94.13
TOTAL
721.64
Add Cess @ 1% on “Z”
+7.22
Cost of each cut
728.86
SAY
₹728.85
D-02/SOURCEPRINTED PAGE 1588
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1588

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1588. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.