Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes of Class K - 9 conforming to IS : 8329

300 mm dia Ductile Iron Double Flanged
Item number
18.73.5
Analysis basis
5 metre
Priced inputs
2
Derived rate
₹5,895.70/ METRE
D-01/RATE ANALYSISITEM 18.73.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.73.5 (Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes of Class K - 9 conforming to IS : 8329: 300 mm dia Ductile Iron Double Flanged) is derived from 2 priced inputs for 5 metre and works out to ₹5,895.70 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 300 mm dia. ductile iron pipes double
  • flanged
  • Weight of 1 m pipes = 76.400 Kg
  • Weight of 5 m pipes 76.400x5 = 382.00
  • Kg
ANALYSIS OF RATES · ITEM 18.73.5DETAILS OF COST FOR 5 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7690MATDuctile Iron Pipe Class K-9 flanges and welding 300mm diaDuctile Iron Pipe Class K-9 flanges and welding 300 mm diametre53,950.0019,750.00
SUBRate as per Item Number 18.23 of SH: Water SupplyRate as per item 18.23quintal3.82361.651,381.50
BUILD-UP TO RATE
TOTAL
21,131.50
Add 1 % Water charges on “W-A”
+197.50
TOTAL
21,329.00
Add GST on “X-A” (multiplying factor 0.2127)
+4,242.83
TOTAL
25,571.83
Add 15% CPOH on “Y-A”
+3,628.55
TOTAL
29,200.38
Add Cess @ 1% on “Z-A”
+278.19
Cost of 5 metre
29,478.57
Cost per metre
5,895.71
SAY
₹5,895.70
D-02/SOURCEPRINTED PAGE 1560
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1560

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1560. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.