R/DAR 2023

Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes of Class K - 9 conforming to IS : 8329

150 mm dia Ductile Iron Double Flanged
Item number
18.73.2
Analysis basis
5 metre
Priced inputs
2
Derived rate
₹2,607.50/ METRE
D-01/RATE ANALYSISITEM 18.73.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.73.2 (Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes of Class K - 9 conforming to IS : 8329: 150 mm dia Ductile Iron Double Flanged) is derived from 2 priced inputs for 5 metre and works out to ₹2,607.50 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 150 mm dia. ductile iron pipes double
  • flanged
  • Weight of 1 m pipes = 32.600 Kg
  • Weight of 5 m pipes 32.600x5 = 163.00
  • Kg
ANALYSIS OF RATES · ITEM 18.73.2DETAILS OF COST FOR 5 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7687MATDuctile Iron Pipe Class K-9 flanges and welding 150 diaDuctile Iron Pipe Class K-9 flanges and welding 150 mm diametre51,750.008,750.00
SUBRate as per Item Number 18.23 of SH: Water SupplyRate as per item 18.23quintal1.63361.65589.49
BUILD-UP TO RATE
TOTAL
9,339.49
Add 1 % Water charges on “W-A”
+87.50
TOTAL
9,426.99
Add GST on “X-A” (multiplying factor 0.2127)
+1,879.74
TOTAL
11,306.73
Add 15% CPOH on “Y-A”
+1,607.59
TOTAL
12,914.32
Add Cess @ 1% on “Z-A”
+123.25
Cost of 5 metre
13,037.57
Cost per metre
2,607.51
SAY
₹2,607.50
D-02/SOURCEPRINTED PAGE 1559
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1559

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1559. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.