Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes of Class K - 9 conforming to IS : 8329

100 mm dia Ductile Iron Double Flanged
Item number
18.73.1
Analysis basis
5 metre
Priced inputs
2
Derived rate
₹1,821.55/ METRE
D-01/RATE ANALYSISITEM 18.73.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.73.1 (Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes of Class K - 9 conforming to IS : 8329: 100 mm dia Ductile Iron Double Flanged) is derived from 2 priced inputs for 5 metre and works out to ₹1,821.55 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 100 mm dia. ductile iron pipes double
  • flanged
  • Weight of 1 m pipes = 21.700 Kg
  • Weight of 5 m pipes 21.700x5 = 108.50
  • Kg
ANALYSIS OF RATES · ITEM 18.73.1DETAILS OF COST FOR 5 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7686MATDuctile Iron Pipe Class K-9 flanges and welding 100mm diaDuctile Iron Pipe Class K-9 flanges and welding 100 mm diametre51,225.006,125.00
SUBRate as per Item Number 18.23 of SH: Water SupplyRate as per item 18.23quintal1.09361.65394.20
BUILD-UP TO RATE
TOTAL
6,519.20
Add 1 % Water charges on “W-A”
+61.25
TOTAL
6,580.45
Add GST on “X-A” (multiplying factor 0.2127)
+1,315.82
TOTAL
7,896.27
Add 15% CPOH on “Y-A”
+1,125.31
TOTAL
9,021.58
Add Cess @ 1% on “Z-A”
+86.27
Cost of 5 metre
9,107.85
Cost per metre
1,821.57
SAY
₹1,821.55
D-02/SOURCEPRINTED PAGE 1558
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1558

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1558. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.