Providing, laying, jointing and testing S&S Centrifugally Cast Ductile Iron double chamber Class K-9 pressure pipes conforming to IS 8329:2000 with restrained joints (bolt less), all complete

450 mm nominal dia pipe

Item number
18.72A.8
Analysis basis
Details of cost for 10 metre
Priced inputs
6
Derived rate
9,861.20 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.72A.8 Providing, laying, jointing and testing S&S Centrifugally Cast Ductile Iron double chamber Class K-9 pressure pipes conforming to IS 8329:2000 with restrained joints (bolt less), all complete 450 mm nominal dia pipe — is derived from 6 priced inputs for 10 metre and works out to ₹9,861.20 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • 450 mm dia Centrifugally Cast Ductile Iron
  • restrained joint class K9 pipes (in 5.5 m
  • lengths)
  • Weight of 1 m pipes = 116.52 Kg
  • Weight of 10 m pipes=1165.2 Kg
  • Labour for laying and jointing
CodeInputUnitQuantityRate (INR)Amount (INR)
7598Centrifugally Cast DI class K9 pipe including double chamber restraining arrangements (bolt less) 450 mm nominal dia pipeCentrifugally Cast DI class K9 pipe including double chamber restraining arrangements (bolt less) 450 mm nominal dia pipeMaterialmetre106,629.0066,290.00
7613Rubber Gasket of EPDM quality for 450 mm nominal dia pipeRubber Gasket of EPDM quality for 450 mm nominal dia pipeMaterialeach2250.00500.00
0116Fitter (grade 1)Labourday0.28897.00251.16
0117Assistant Fitter or 2nd class FitterLabourday0.57816.00465.12
0114BeldarLabourday2.38736.001,751.68
9999SundriesMaterialL.S.25.752.2758.45
TOTAL
69,316.41
Add 1 % Water charges on “W”
693.16
TOTAL
70,009.57
Add GST on “X” (multiplying factor 0.2127)
14,891.04
TOTAL
84,900.61
Add 15% CPOH on “Y”
12,735.09
TOTAL
97,635.70
Add Cess @ 1% on “Z”
976.36
Cost of 10 metre
98,612.06
Cost of 1.00 metre
9,861.21
Say
9,861.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1553. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.