Skip to main content
R/DAR 2023

Providing, laying, jointing and testing S&S Centrifugally Cast Ductile Iron double chamber Class K-9 pressure pipes conforming to IS 8329:2000 with restrained joints (bolt less), all complete

350 mm nominal dia pipe
Item number
18.72A.6
Analysis basis
10 metre
Priced inputs
6
Derived rate
₹6,636.80/ METRE
D-01/RATE ANALYSISITEM 18.72A.6

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.72A.6 (Providing, laying, jointing and testing S&S Centrifugally Cast Ductile Iron double chamber Class K-9 pressure pipes conforming to IS 8329:2000 with restrained joints (bolt less), all complete 350 mm nominal dia pipe) is derived from 6 priced inputs for 10 metre and works out to ₹6,636.80 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 350 mm dia Centrifugally Cast Ductile Iron
  • restrained joint class K9 pipes (in 5.5 m
  • lengths)
  • Weight of 1 m pipes = 83.72 Kg
  • Weight of 10 m pipes=837.2 Kg
  • Labour for laying and jointing
ANALYSIS OF RATES · ITEM 18.72A.6DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7596MATCentrifugally Cast DI class K9 pipe including double chamber restraining arrangements (bolt less) 350 mm nominal dia pipeCentrifugally Cast DI class K9 pipe including double chamber restraining arrangements (bolt less) 350 mm nominal dia pipemetre104,480.0044,800.00
7611MATRubber Gasket of EPDM quality for 350 mm nominal dia pipeRubber Gasket of EPDM quality for 350 mm nominal dia pipeeach2116.00232.00
0116LABFitter (grade 1)day0.18897.00161.46
0117LABAssistant Fitter or 2nd class Fitterday0.37816.00301.92
0114LABBeldarday1.52736.001,118.72
9999MATSundriesL.S.16.482.2737.41
BUILD-UP TO RATE
TOTAL
46,651.51
Add 1 % Water charges on “W”
+466.52
TOTAL
47,118.03
Add GST on “X” (multiplying factor 0.2127)
+10,022.00
TOTAL
57,140.03
Add 15% CPOH on “Y”
+8,571.00
TOTAL
65,711.03
Add Cess @ 1% on “Z”
+657.11
Cost of 10 metre
66,368.14
Cost of 1.00 metre
6,636.81
SAY
₹6,636.80
D-02/SOURCEPRINTED PAGE 1552
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1552

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1552. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.