Skip to main content
R/DAR 2023

Providing and laying Double Flanged (screwed / welded) Centrifugally (Spun) Cast Iron, Class B (IS : 1536)

500 mm dia C.I. Double Flanged Pipe
Item number
18.71.9
Analysis basis
5 metre
Priced inputs
2
Derived rate
₹21,619.65/ METRE
D-01/RATE ANALYSISITEM 18.71.9

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.71.9 (Providing and laying Double Flanged (screwed / welded) Centrifugally (Spun) Cast Iron, Class B (IS : 1536) : 500 mm dia C.I. Double Flanged Pipe) is derived from 2 priced inputs for 5 metre and works out to ₹21,619.65 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 500 mm dia. cast iron pipes double
  • flanged
  • Weight of 1 m pipes = 234.80 Kg
  • Weight of 5 m pipes 234.80x5 = 1174.00
  • Kg
ANALYSIS OF RATES · ITEM 18.71.9DETAILS OF COST FOR 5 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7720MATScrewed double flanged centrigually cast (spun) C.I. Pipe of Class B conforming to I.S. 1536, - 500mm diaScrewed double flanged centrifugally cast (spun) C./. Pipe of Class B conforming to I.S. 1536, - 500 mm diametre514,600.0073,000.00
SUBRate same as per item no 18.23 of SH: Water SupplyRate as per item 18.23quintal11.74361.654,245.77
BUILD-UP TO RATE
TOTAL
77,245.77
Add 1 % Water charges on “W-A”
+730.00
TOTAL
77,975.77
Add GST on “X-A” (multiplying factor 0.2127)
+15,682.37
TOTAL
93,658.14
Add 15% CPOH on “Y-A”
+13,411.86
TOTAL
1,07,070.00
Add Cess @ 1% on “Z-A”
+1,028.24
Cost of 5 metre
1,08,098.24
Cost per metre
21,619.65
SAY
₹21,619.65
D-02/SOURCEPRINTED PAGE 1534
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1534

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1534. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.