CPWD Analysis of Rates · Water Supply

Providing and laying Double Flanged (screwed / welded) Centrifugally (Spun) Cast Iron, Class B (IS : 1536)

600 mm dia C.I. Double Flanged Pipe

Item number
18.71.10
Analysis basis
Details of cost for 5 metre
Priced inputs
2
Derived rate
27,459.40 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.71.10 Providing and laying Double Flanged (screwed / welded) Centrifugally (Spun) Cast Iron, Class B (IS : 1536) : 600 mm dia C.I. Double Flanged Pipe — is derived from 2 priced inputs for 5 metre and works out to ₹27,459.40 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • 600 mm dia. cast iron pipes double
  • flanged
  • Weight of 1 m pipes = 315.30 Kg
  • Weight of 5 m pipes 315.30x5 = 1576.50
  • Kg
CodeInputUnitQuantityRate (INR)Amount (INR)
7721Screwed double flanged centrigually cast (spun) C.I. Pipe of Class B conforming to I.S. 1536, - 600mm diaScrewed double flanged centrifugally cast (spun) C.I. Pipe of Class B conforming to I.S. 1536, - 600 mm diaMaterialmetre518,500.0092,500.00
Rate same as per item no 18.23 of SH: Water SupplyRate as per item 18.23Sub-analysisquintal15.77361.655,703.22
TOTAL
98,203.22
Add 1 % Water charges on “W-A”
925.00
TOTAL
99,128.22
Add GST on “X-A” (multiplying factor 0.2127)
19,871.50
TOTAL
1,18,999.72
Add 15% CPOH on “Y-A”
16,994.48
TOTAL
1,35,994.20
Add Cess @ 1% on “Z-A”
1,302.91
Cost of 5 metre
1,37,297.11
Cost per metre
27,459.42
Say
27,459.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1534. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.