Providing and laying Double Flanged (screwed / welded) Centrifugally (Spun) Cast Iron, Class B (IS : 1536)
- Item number
- 18.71.7
- Analysis basis
- 5 metre
- Priced inputs
- 2
- Derived rate
- ₹13,136.65/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.71.7 (Providing and laying Double Flanged (screwed / welded) Centrifugally (Spun) Cast Iron, Class B (IS : 1536) : 400 mm dia C.I. Double Flanged Pipe) is derived from 2 priced inputs for 5 metre and works out to ₹13,136.65 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- 400 mm dia. cast iron pipes double
- flanged
- Weight of 1 m pipes = 166.80 Kg
- Weight of 5 m pipes 166.80x5 = 834.00
- Kg
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7718 | MAT | Screwed double flanged centrigually cast (spun) C.I. Pipe of Class B conforming to I.S. 1536, - 400mm diaScrewed double flanged centrifugally cast (spun) C.I. Pipe of Class B conforming to I.S. 1536, - 400 mm dia | metre | 5 | 8,810.00 | 44,050.00 |
| SUB | Rate same as per item no 18.23 of SH: Water SupplyRate as per item 18.23 | quintal | 8.34 | 361.65 | 3,016.16 |
- TOTAL
- 47,066.16
- Add 1 % Water charges on “W-A”
- +440.50
- TOTAL
- 47,506.66
- Add GST on “X-A” (multiplying factor 0.2127)
- +9,463.13
- TOTAL
- 56,969.79
- Add 15% CPOH on “Y-A”
- +8,093.04
- TOTAL
- 65,062.83
- Add Cess @ 1% on “Z-A”
- +620.47
- Cost of 5 metre
- 65,683.30
- Cost per metre
- 13,136.66
- SAY
- ₹13,136.65
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1533
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1533. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.