Providing and laying Double Flanged (screwed / welded) Centrifugally (Spun) Cast Iron, Class B (IS : 1536)

350 mm dia C.I. Double Flanged Pipe
Item number
18.71.6
Analysis basis
5 metre
Priced inputs
2
Derived rate
₹10,093.90/ METRE
D-01/RATE ANALYSISITEM 18.71.6

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.71.6 (Providing and laying Double Flanged (screwed / welded) Centrifugally (Spun) Cast Iron, Class B (IS : 1536) : 350 mm dia C.I. Double Flanged Pipe) is derived from 2 priced inputs for 5 metre and works out to ₹10,093.90 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 350 mm dia. cast iron pipes double
  • flanged
  • Weight of 1 m pipes = 135.70 Kg
  • Weight of 5 m pipes 135.70x5 = 678.50
  • Kg
ANALYSIS OF RATES · ITEM 18.71.6DETAILS OF COST FOR 5 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7717MATScrewed double flanged centrigually cast (spun) C.I. Pipe of Class B conforming to I.S. 1536, - 350mm diaScrewed double flanged centrifugally cast (spun) C.I. Pipe of Class B conforming to I.S. 1536, - 350 mm diametre56,750.0033,750.00
SUBRate same as per item no 18.23 of SH: Water SupplyRate as per item 18.23quintal6.79361.652,455.60
BUILD-UP TO RATE
TOTAL
36,205.60
Add 1 % Water charges on “W-A”
+337.50
TOTAL
36,543.10
Add GST on “X-A” (multiplying factor 0.2127)
+7,250.41
TOTAL
43,793.51
Add 15% CPOH on “Y-A”
+6,200.69
TOTAL
49,994.20
Add Cess @ 1% on “Z-A”
+475.39
Cost of 5 metre
50,469.59
Cost per metre
10,093.92
SAY
₹10,093.90
D-02/SOURCEPRINTED PAGE 1532
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1532

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1532. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.