Providing and laying Double Flanged (screwed / welded) Centrifugally (Spun) Cast Iron, Class B (IS : 1536)
- Item number
- 18.71.1
- Analysis basis
- 5 metre
- Priced inputs
- 2
- Derived rate
- ₹2,089.35/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.71.1 (Providing and laying Double Flanged (screwed / welded) Centrifugally (Spun) Cast Iron, Class B (IS : 1536) : 100 mm dia C.I. Double Flanged Pipe) is derived from 2 priced inputs for 5 metre and works out to ₹2,089.35 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- 100 mm dia. cast iron pipes double
- flanged = 27.00 Kg
- Weight of 5 m pipes 27.00x5 = 135.00 Kg
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7712 | MAT | Screwed double flanged centrigually cast (spun) C.I. Pipe of Class B conforming to I.S. 1536, - 100mm diaScrewed double flanged centrifugally cast (spun) C.I. Pipe of Class B conforming to I.S. 1536, - 100 mm dia | metre | 5 | 1,400.00 | 7,000.00 |
| SUB | Rate same as per item no 18.23 of SH: Water SupplyRate as per item 18.23 | quintal | 1.35 | 361.65 | 488.23 |
- TOTAL
- 7,488.23
- Add 1 % Water charges on “W-A”
- +70.00
- TOTAL
- 7,558.23
- Add GST on “X-A” (multiplying factor 0.2127)
- +1,503.79
- TOTAL
- 9,062.02
- Add 15% CPOH on “Y-A”
- +1,286.07
- TOTAL
- 10,348.09
- Add Cess @ 1% on “Z-A”
- +98.60
- Cost of 5 metre
- 10,446.69
- Cost of metre
- 2,089.34
- SAY
- ₹2,089.35
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1530
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1530. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.