Providing and laying Double Flanged (screwed / welded) Centrifugally (Spun) Cast Iron, Class B (IS : 1536)

100 mm dia C.I. Double Flanged Pipe
Item number
18.71.1
Analysis basis
5 metre
Priced inputs
2
Derived rate
₹2,089.35/ METRE
D-01/RATE ANALYSISITEM 18.71.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.71.1 (Providing and laying Double Flanged (screwed / welded) Centrifugally (Spun) Cast Iron, Class B (IS : 1536) : 100 mm dia C.I. Double Flanged Pipe) is derived from 2 priced inputs for 5 metre and works out to ₹2,089.35 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 100 mm dia. cast iron pipes double
  • flanged = 27.00 Kg
  • Weight of 5 m pipes 27.00x5 = 135.00 Kg
ANALYSIS OF RATES · ITEM 18.71.1DETAILS OF COST FOR 5 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7712MATScrewed double flanged centrigually cast (spun) C.I. Pipe of Class B conforming to I.S. 1536, - 100mm diaScrewed double flanged centrifugally cast (spun) C.I. Pipe of Class B conforming to I.S. 1536, - 100 mm diametre51,400.007,000.00
SUBRate same as per item no 18.23 of SH: Water SupplyRate as per item 18.23quintal1.35361.65488.23
BUILD-UP TO RATE
TOTAL
7,488.23
Add 1 % Water charges on “W-A”
+70.00
TOTAL
7,558.23
Add GST on “X-A” (multiplying factor 0.2127)
+1,503.79
TOTAL
9,062.02
Add 15% CPOH on “Y-A”
+1,286.07
TOTAL
10,348.09
Add Cess @ 1% on “Z-A”
+98.60
Cost of 5 metre
10,446.69
Cost of metre
2,089.34
SAY
₹2,089.35
D-02/SOURCEPRINTED PAGE 1530
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1530

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1530. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.