Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including testing of joints and the cost of rubber gasket

1000 mm dia pipes
Item number
18.70.15
Analysis basis
50 Joints
Priced inputs
4
Derived rate
₹2,604.40/ JOINT
D-01/RATE ANALYSISITEM 18.70.15

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.70.15 (Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including testing of joints and the cost of rubber gasket: 1000 mm dia pipes) is derived from 4 priced inputs for 50 Joints and works out to ₹2,604.40 per joint after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 18.70.15DETAILS OF COST FOR 50 JOINTS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7681MATRuber Gaskets Conforming to I.S 5382 of S.B.R quality 1000mm diaRubber Gaskets Conforming to I.S 5382 of S.B.R quality 1000 mm diaeach501,130.0056,500.00
0116LABFitter (grade 1)day11897.009,867.00
0117LABAssistant Fitter or 2nd class Fitterday11816.008,976.00
0114LABBeldarday22736.0016,192.00
BUILD-UP TO RATE
TOTAL
91,535.00
Add 1 % Water charges on “W”
+915.35
TOTAL
92,450.35
Add GST on “X” (multiplying factor 0.2127)
+19,664.19
TOTAL
1,12,114.54
Add 15% CPOH on “Y”
+16,817.18
TOTAL
1,28,931.72
Add Cess @ 1% on “Z”
+1,289.32
Cost of 50 joints
1,30,221.04
Cost of 1 joint
2,604.42
SAY
₹2,604.40
D-02/SOURCEPRINTED PAGE 1530
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1530

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1530. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.