Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including testing of joints and the cost of rubber gasket

700 mm dia pipes
Item number
18.70.11
Analysis basis
50 Joints
Priced inputs
4
Derived rate
₹1,572.70/ JOINT
D-01/RATE ANALYSISITEM 18.70.11

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.70.11 (Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including testing of joints and the cost of rubber gasket: 700 mm dia pipes) is derived from 4 priced inputs for 50 Joints and works out to ₹1,572.70 per joint after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 18.70.11DETAILS OF COST FOR 50 JOINTS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7677MATRuber Gaskets Conforming to I.S 5382 of S.B.R quality 700mm diaRubber Gaskets Conforming to I.S 5382 of S.B.R quality 700 mm diaeach50615.0030,750.00
0116LABFitter (grade 1)day7.7897.006,906.90
0117LABAssistant Fitter or 2nd class Fitterday7.7816.006,283.20
0114LABBeldarday15.4736.0011,334.40
BUILD-UP TO RATE
TOTAL
55,274.50
Add 1 % Water charges on “W”
+552.75
TOTAL
55,827.25
Add GST on “X” (multiplying factor 0.2127)
+11,874.46
TOTAL
67,701.71
Add 15% CPOH on “Y”
+10,155.26
TOTAL
77,856.97
Add Cess @ 1% on “Z”
+778.57
Cost of 50 joints
78,635.54
Cost of 1 joint
1,572.71
SAY
₹1,572.70
D-02/SOURCEPRINTED PAGE 1528
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1528

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1528. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.