Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including testing of joints and the cost of rubber gasket
- Item number
- 18.70.11
- Analysis basis
- 50 Joints
- Priced inputs
- 4
- Derived rate
- ₹1,572.70/ JOINT
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.70.11 (Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including testing of joints and the cost of rubber gasket: 700 mm dia pipes) is derived from 4 priced inputs for 50 Joints and works out to ₹1,572.70 per joint after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7677 | MAT | Ruber Gaskets Conforming to I.S 5382 of S.B.R quality 700mm diaRubber Gaskets Conforming to I.S 5382 of S.B.R quality 700 mm dia | each | 50 | 615.00 | 30,750.00 |
| 0116 | LAB | Fitter (grade 1) | day | 7.7 | 897.00 | 6,906.90 |
| 0117 | LAB | Assistant Fitter or 2nd class Fitter | day | 7.7 | 816.00 | 6,283.20 |
| 0114 | LAB | Beldar | day | 15.4 | 736.00 | 11,334.40 |
- TOTAL
- 55,274.50
- Add 1 % Water charges on “W”
- +552.75
- TOTAL
- 55,827.25
- Add GST on “X” (multiplying factor 0.2127)
- +11,874.46
- TOTAL
- 67,701.71
- Add 15% CPOH on “Y”
- +10,155.26
- TOTAL
- 77,856.97
- Add Cess @ 1% on “Z”
- +778.57
- Cost of 50 joints
- 78,635.54
- Cost of 1 joint
- 1,572.71
- SAY
- ₹1,572.70
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1528
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1528. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.