Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including testing of joints and the cost of rubber gasket
- Item number
- 18.70.10
- Analysis basis
- 50 Joints
- Priced inputs
- 4
- Derived rate
- ₹1,207.90/ JOINT
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.70.10 (Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including testing of joints and the cost of rubber gasket: 600 mm dia pipes) is derived from 4 priced inputs for 50 Joints and works out to ₹1,207.90 per joint after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7676 | MAT | Ruber Gaskets Conforming to I.S 5382 of S.B.R quality 600mm diaRubber Gaskets Conforming to I.S 5382 of S.B.R quality 600 mm dia | each | 50 | 435.00 | 21,750.00 |
| 0116 | LAB | Fitter (grade 1) | day | 6.5 | 897.00 | 5,830.50 |
| 0117 | LAB | Assistant Fitter or 2nd class Fitter | day | 6.5 | 816.00 | 5,304.00 |
| 0114 | LAB | Beldar | day | 13 | 736.00 | 9,568.00 |
- TOTAL
- 42,452.50
- Add 1 % Water charges on “W”
- +424.53
- TOTAL
- 42,877.03
- Add GST on “X” (multiplying factor 0.2127)
- +9,119.94
- TOTAL
- 51,996.97
- Add 15% CPOH on “Y”
- +7,799.55
- TOTAL
- 59,796.52
- Add Cess @ 1% on “Z”
- +597.97
- Cost of 50 joints
- 60,394.49
- Cost of 1 joint
- 1,207.89
- SAY
- ₹1,207.90
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1527
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1527. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.