Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply and all CPVC plain & brass threaded fittings, including fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and testing of joints complete as per direction of Engineer in Charge. Internal work - Exposed on wall
- Item number
- 18.7.6
- Analysis basis
- 10 metre
- Priced inputs
- 5
- Derived rate
- ₹934.15/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.7.6 (Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply and all CPVC plain & brass threaded fittings, including fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and testing of joints complete as per direction of Engineer in Charge. Internal work - Exposed on wall 50 mm nominal dia Pipes) is derived from 5 priced inputs for 10 metre and works out to ₹934.15 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- 30 x P / 100
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8641 | MAT | Chlorinated Polyvinyl - chloride (CPVC) pipe 50 mm nominal dia | metre | 10 | 325.00 | 3,250.00 |
| 9999 | MAT | Cement, sand and grit etc. | L.S. | 5.33 | 2.27 | 12.10 |
| 0116 | LAB | Fitter (grade 1) | day | 0.33 | 897.00 | 296.01 |
| 0117 | LAB | Assistant Fitter or 2nd class Fitter | day | 1.31 | 816.00 | 1,068.96 |
| 0114 | LAB | Beldar | day | 1.31 | 736.00 | 964.16 |
- Add 30% for fittings and wastage etc. on (P)
- +975.00
- TOTAL
- 6,566.23
- Add 1 % Water charges on “W”
- +65.66
- TOTAL
- 6,631.89
- Add GST on “X” (multiplying factor 0.2127)
- +1,410.60
- TOTAL
- 8,042.49
- Add 15% CPOH on “Y”
- +1,206.37
- TOTAL
- 9,248.86
- Add Cess @ 1% on “Z”
- +92.49
- Cost of 10 metre
- 9,341.35
- Cost of 1 metre
- 934.14
- SAY
- ₹934.15
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1418
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1418. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.