CPWD Analysis of Rates · Water Supply

Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply and all CPVC plain & brass threaded fittings, including fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and testing of joints complete as per direction of Engineer in Charge. Internal work - Exposed on wall

40 mm nominal dia Pipes

Item number
18.7.5
Analysis basis
Details of cost for 10 metre
Priced inputs
5
Derived rate
702.95 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.7.5 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply and all CPVC plain & brass threaded fittings, including fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and testing of joints complete as per direction of Engineer in Charge. Internal work - Exposed on wall 40 mm nominal dia Pipes — is derived from 5 priced inputs for 10 metre and works out to ₹702.95 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • 30 x P / 100
CodeInputUnitQuantityRate (INR)Amount (INR)
8640Chlorinated Polyvinyl - chloride (CPVC) pipe 40 mm nominal diaMaterialmetre10200.002,000.00
9999Cement, sand and grit etc.MaterialL.S.5.332.2712.10
0116Fitter (grade 1)Labourday0.33897.00296.01
0117Assistant Fitter or 2nd class FitterLabourday1.31816.001,068.96
0114BeldarLabourday1.31736.00964.16
Add 30% for fittings and wastage etc. on (P)
600.00
TOTAL
4,941.23
Add 1 % Water charges on “W”
49.41
TOTAL
4,990.64
Add GST on “X” (multiplying factor 0.2127)
1,061.51
TOTAL
6,052.15
Add 15% CPOH on “Y”
907.82
TOTAL
6,959.97
Add Cess @ 1% on “Z”
69.60
Cost of 10 metre
7,029.57
Cost of 1 metre
702.96
Say
702.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1417. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.