Providing and fixing PPR Unions

PPR Union 50mm
Item number
18.6A.5
Analysis basis
1 No
Priced inputs
4
Derived rate
₹782.10/ NO
D-01/RATE ANALYSISITEM 18.6A.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.6A.5 (Providing and fixing PPR Unions PPR Union 50mm) is derived from 4 priced inputs for 1 No and works out to ₹782.10 per no after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • MATERIAL:
  • LABOUR:
ANALYSIS OF RATES · ITEM 18.6A.5DETAILS OF COST FOR 1 NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8310MATPPR Union 50mmPPR Union 50 mmeach1366.00366.00
9999MATCarriage of materials and sundriesL.S.1.822.274.13
0116LABFitter (grade 1)day0.11897.0098.67
0114LABBeldarday0.11736.0080.96
BUILD-UP TO RATE
TOTAL
549.76
Add 1 % Water charges on “W”
+5.50
TOTAL
555.26
Add GST on “X” (multiplying factor 0.2127)
+118.10
TOTAL
673.36
Add 15% CPOH on “Y”
+101.00
TOTAL
774.36
Add Cess @ 1% on “Z”
+7.74
Cost of 1 No
782.10
SAY
₹782.10
D-02/SOURCEPRINTED PAGE 1414
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1414

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1414. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.