CPWD Analysis of Rates · Water Supply

Providing and fixing PPR Unions

PPR Union 50mm

Item number
18.6A.5
Analysis basis
Details of cost for 1 No
Priced inputs
4
Derived rate
782.10 / No

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.6A.5 Providing and fixing PPR Unions PPR Union 50mm — is derived from 4 priced inputs for 1 No and works out to ₹782.10 per no after water charges, GST, CPOH and cess. The full build-up is below.

  • MATERIAL:
  • LABOUR:
CodeInputUnitQuantityRate (INR)Amount (INR)
8310PPR Union 50mmPPR Union 50 mmMaterialeach1366.00366.00
9999Carriage of materials and sundriesMaterialL.S.1.822.274.13
0116Fitter (grade 1)Labourday0.11897.0098.67
0114BeldarLabourday0.11736.0080.96
TOTAL
549.76
Add 1 % Water charges on “W”
5.50
TOTAL
555.26
Add GST on “X” (multiplying factor 0.2127)
118.10
TOTAL
673.36
Add 15% CPOH on “Y”
101.00
TOTAL
774.36
Add Cess @ 1% on “Z”
7.74
Cost of 1 No
782.10
Say
782.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1414. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.