Skip to main content

CPWD Analysis of Rates · Water Supply

Providing and fixing PPR Unions

PPR Union 20mm

Item number
18.6A.1
Analysis basis
Details of cost for 1 No
Priced inputs
4
Derived rate
315.50 / No

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.6A.1 Providing and fixing PPR Unions PPR Union 20mm — is derived from 4 priced inputs for 1 No and works out to ₹315.50 per no after water charges, GST, CPOH and cess. The full build-up is below.

  • MATERIAL:
  • LABOUR:
CodeInputUnitQuantityRate (INR)Amount (INR)
8306PPR Union 20mmPPR Union 20 mmMaterialeach138.0038.00
9999Carriage of materials and sundriesMaterialL.S.1.822.274.13
0116Fitter (grade 1)Labourday0.11897.0098.67
0114BeldarLabourday0.11736.0080.96
TOTAL
221.76
Add 1 % Water charges on “W”
2.22
TOTAL
223.98
Add GST on “X” (multiplying factor 0.2127)
47.64
TOTAL
271.62
Add 15% CPOH on “Y”
40.74
TOTAL
312.36
Add Cess @ 1% on “Z”
3.12
Cost of 1 No
315.48
Say
315.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 9999. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works