Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes conforming to IS:15801 UV stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply, including all PP - R plain & brass threaded polypropylene random fittings, including trenching, refilling & testing of joints complete as per direction of Engineer-inCharge. External work
- Item number
- 18.6.10
- Analysis basis
- 10 metre
- Priced inputs
- 5
- Derived rate
- ₹2,746.85/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.6.10 (Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes conforming to IS:15801 UV stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply, including all PP - R plain & brass threaded polypropylene random fittings, including trenching, refilling & testing of joints complete as per direction of Engineer-inCharge. External work PN - 10 Pipe, 160 mm OD (SDR-11)) is derived from 5 priced inputs for 10 metre and works out to ₹2,746.85 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- MATERIAL:
- LABOUR:
- Trenching and refilling etc.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8635 | MAT | Poly propyleneRandom - Co - Polymer (PPR) pipes PN-10 (SDR 11) - 160 mm Outer diaPoly propylene- Random - Co - Polymer (PPR) pipes PN-10 (SDR 11) - 160 mm Outer dia | metre | 10 | 1,324.00 | 13,240.00 |
| 0116 | LAB | Fitter (grade 1) | day | 0.58 | 897.00 | 520.26 |
| 0114 | LAB | Beldar | day | 1.54 | 736.00 | 1,133.44 |
| 0114 | LAB | Beldar | day | 1.2 | 736.00 | 883.20 |
| 0115 | LAB | Coolie | day | 1.2 | 736.00 | 883.20 |
- Add 20% for fittings and wastage etc. on P, 20xP/100
- +2,648.00
- TOTAL
- 19,308.10
- Add 1 % Water charges on “W”
- +193.08
- TOTAL
- 19,501.18
- Add GST on “X” (multiplying factor 0.2127)
- +4,147.90
- TOTAL
- 23,649.08
- Add 15% CPOH on “Y”
- +3,547.36
- TOTAL
- 27,196.44
- Add Cess @ 1% on “Z”
- +271.96
- Cost of 10 metre
- 27,468.40
- Cost of 1 metre
- 2,746.84
- SAY
- ₹2,746.85
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1412
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1412. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.