Skip to main content

CPWD Analysis of Rates · Water Supply

Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes conforming to IS:15801 UV stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply, including all PP - R plain & brass threaded polypropylene random fittings, including trenching, refilling & testing of joints complete as per direction of Engineer-inCharge. External work

PN - 10 Pipe, 160 mm OD (SDR-11)

Item number
18.6.10
Analysis basis
Details of cost for 10 metre
Priced inputs
5
Derived rate
2,746.85 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.6.10 Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes conforming to IS:15801 UV stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply, including all PP - R plain & brass threaded polypropylene random fittings, including trenching, refilling & testing of joints complete as per direction of Engineer-inCharge. External work PN - 10 Pipe, 160 mm OD (SDR-11) — is derived from 5 priced inputs for 10 metre and works out to ₹2,746.85 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • MATERIAL:
  • LABOUR:
  • Trenching and refilling etc.
CodeInputUnitQuantityRate (INR)Amount (INR)
8635Poly propyleneRandom - Co - Polymer (PPR) pipes PN-10 (SDR 11) - 160 mm Outer diaPoly propylene- Random - Co - Polymer (PPR) pipes PN-10 (SDR 11) - 160 mm Outer diaMaterialmetre101,324.0013,240.00
0116Fitter (grade 1)Labourday0.58897.00520.26
0114BeldarLabourday1.54736.001,133.44
0114BeldarLabourday1.2736.00883.20
0115CoolieLabourday1.2736.00883.20
Add 20% for fittings and wastage etc. on P, 20xP/100
2,648.00
TOTAL
19,308.10
Add 1 % Water charges on “W”
193.08
TOTAL
19,501.18
Add GST on “X” (multiplying factor 0.2127)
4,147.90
TOTAL
23,649.08
Add 15% CPOH on “Y”
3,547.36
TOTAL
27,196.44
Add Cess @ 1% on “Z”
271.96
Cost of 10 metre
27,468.40
Cost of 1 metre
2,746.84
Say
2,746.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1412. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works