Providing and laying Class K-12 Ductile Iron double chamber restrained joint (bolt less) specials such as tees, bends, collars, tapers and caps etc. conforming to IS 9523 including testing of joints all complete
- Item number
- 18.68A.2
- Analysis basis
- 1 quintal
- Priced inputs
- 2
- Derived rate
- ₹39,073.05/ QUINTAL
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.68A.2 (Providing and laying Class K-12 Ductile Iron double chamber restrained joint (bolt less) specials such as tees, bends, collars, tapers and caps etc. conforming to IS 9523 including testing of joints all complete Above 600 mm nominal dia) is derived from 2 priced inputs for 1 quintal and works out to ₹39,073.05 per quintal after water charges, GST, CPOH and cess. The full build-up is below.
- Ductile Iron restrain Joint
- K - 12 specials suitable for push on
- jointing above 600 mm dia
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7590 | MAT | Ductile Iron double chamber restrained joint (bolt less) fittings class K12 above 600 mm nominal dia | quintal | 1 | 27,000.00 | 27,000.00 |
| SUB | Rate as per Item Number 18.24 of SH: Water SupplyRate as per item 18.24 | quintal | 1 | 661.85 | 661.85 |
- TOTAL
- 27,661.85
- Add 1 % Water charges on “W-A”
- +270.00
- TOTAL
- 27,931.85
- Add GST on “X-A” (multiplying factor 0.2127)
- +5,800.33
- TOTAL
- 33,732.18
- Add 15% CPOH on “Y-A”
- +4,960.55
- TOTAL
- 38,692.73
- Add Cess @ 1% on “Z-A”
- +380.31
- Cost of 1 quintal
- 39,073.04
- SAY
- ₹39,073.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1522
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1522. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.