Providing and laying Class K-12 Ductile Iron double chamber restrained joint (bolt less) specials such as tees, bends, collars, tapers and caps etc. conforming to IS 9523 including testing of joints all complete

Above 600 mm nominal dia
Item number
18.68A.2
Analysis basis
1 quintal
Priced inputs
2
Derived rate
₹39,073.05/ QUINTAL
D-01/RATE ANALYSISITEM 18.68A.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.68A.2 (Providing and laying Class K-12 Ductile Iron double chamber restrained joint (bolt less) specials such as tees, bends, collars, tapers and caps etc. conforming to IS 9523 including testing of joints all complete Above 600 mm nominal dia) is derived from 2 priced inputs for 1 quintal and works out to ₹39,073.05 per quintal after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Ductile Iron restrain Joint
  • K - 12 specials suitable for push on
  • jointing above 600 mm dia
ANALYSIS OF RATES · ITEM 18.68A.2DETAILS OF COST FOR 1 QUINTAL
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7590MATDuctile Iron double chamber restrained joint (bolt less) fittings class K12 above 600 mm nominal diaquintal127,000.0027,000.00
SUBRate as per Item Number 18.24 of SH: Water SupplyRate as per item 18.24quintal1661.85661.85
BUILD-UP TO RATE
TOTAL
27,661.85
Add 1 % Water charges on “W-A”
+270.00
TOTAL
27,931.85
Add GST on “X-A” (multiplying factor 0.2127)
+5,800.33
TOTAL
33,732.18
Add 15% CPOH on “Y-A”
+4,960.55
TOTAL
38,692.73
Add Cess @ 1% on “Z-A”
+380.31
Cost of 1 quintal
39,073.04
SAY
₹39,073.05
D-02/SOURCEPRINTED PAGE 1522
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1522

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1522. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.