CPWD Analysis of Rates · Water Supply
Providing and fixing C.I. dirt box strainer for bulk type water meter with nuts, bolts, rubber insertions etc. complete conforming to IS : 2373
200 mm dia
- Item number
- 18.61.4
- Analysis basis
- Details of cost for one no. dirt box stainer
- Priced inputs
- 4
- Derived rate
- ₹12,927.10 / one no
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.61.4 — Providing and fixing C.I. dirt box strainer for bulk type water meter with nuts, bolts, rubber insertions etc. complete conforming to IS : 2373: 200 mm dia — is derived from 4 priced inputs for one no and works out to ₹12,927.10 per one no after water charges, GST, CPOH and cess. The full build-up is below.
- Providing flanged joints to double acting
- air valves with bolts, nuts and rubber
- insertions etc.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7425 | Dirt box srainer 200 mmDirt box strainer 200 mmMaterial | each | 1 | 8,130.00 | 8,130.00 |
| 9977 | Carriage of dirt box strainerMaterial | L.S. | 52 | 2.27 | 118.04 |
| 9999 | Labour for laying dirt box strainerMaterial | L.S. | 104 | 2.27 | 236.08 |
| (Rate as per item no 20.47.5 of SH : Water Supply)Rate as per item 18.30.5Sub-analysis | each | 2 | 428.65 | 857.30 |
- TOTAL
- 9,341.42
- Add 1 % Water charges on “W-A”
- 84.84
- TOTAL
- 9,426.26
- Add GST on “X-A” (multiplying factor 0.2127)
- 1,822.62
- TOTAL
- 11,248.88
- Add 15% CPOH on “Y-A”
- 1,558.74
- TOTAL
- 12,807.62
- Add Cess @ 1% on “Z-A”
- 119.50
- Cost for 10 dirt box stainer
- 12,927.12
- Say
- 12,927.10
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1516. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.