Providing and fixing C.I. dirt box strainer for bulk type water meter with nuts, bolts, rubber insertions etc. complete conforming to IS : 2373

200 mm dia
Item number
18.61.4
Analysis basis
one no
Priced inputs
4
Derived rate
₹12,927.10/ ONE NO
D-01/RATE ANALYSISITEM 18.61.4

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.61.4 (Providing and fixing C.I. dirt box strainer for bulk type water meter with nuts, bolts, rubber insertions etc. complete conforming to IS : 2373: 200 mm dia) is derived from 4 priced inputs for one no and works out to ₹12,927.10 per one no after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Providing flanged joints to double acting
  • air valves with bolts, nuts and rubber
  • insertions etc.
ANALYSIS OF RATES · ITEM 18.61.4DETAILS OF COST FOR ONE NO. DIRT BOX STAINER
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7425MATDirt box srainer 200 mmDirt box strainer 200 mmeach18,130.008,130.00
9977MATCarriage of dirt box strainerL.S.522.27118.04
9999MATLabour for laying dirt box strainerL.S.1042.27236.08
SUB(Rate as per item no 20.47.5 of SH : Water Supply)Rate as per item 18.30.5each2428.65857.30
BUILD-UP TO RATE
TOTAL
9,341.42
Add 1 % Water charges on “W-A”
+84.84
TOTAL
9,426.26
Add GST on “X-A” (multiplying factor 0.2127)
+1,822.62
TOTAL
11,248.88
Add 15% CPOH on “Y-A”
+1,558.74
TOTAL
12,807.62
Add Cess @ 1% on “Z-A”
+119.50
Cost for 10 dirt box stainer
12,927.12
SAY
₹12,927.10
D-02/SOURCEPRINTED PAGE 1516
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1516

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1516. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.