Providing and fixing C.I. dirt box strainer for bulk type water meter with nuts, bolts, rubber insertions etc. complete conforming to IS : 2373
- Item number
- 18.61.4
- Analysis basis
- one no
- Priced inputs
- 4
- Derived rate
- ₹12,927.10/ ONE NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.61.4 (Providing and fixing C.I. dirt box strainer for bulk type water meter with nuts, bolts, rubber insertions etc. complete conforming to IS : 2373: 200 mm dia) is derived from 4 priced inputs for one no and works out to ₹12,927.10 per one no after water charges, GST, CPOH and cess. The full build-up is below.
- Providing flanged joints to double acting
- air valves with bolts, nuts and rubber
- insertions etc.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7425 | MAT | Dirt box srainer 200 mmDirt box strainer 200 mm | each | 1 | 8,130.00 | 8,130.00 |
| 9977 | MAT | Carriage of dirt box strainer | L.S. | 52 | 2.27 | 118.04 |
| 9999 | MAT | Labour for laying dirt box strainer | L.S. | 104 | 2.27 | 236.08 |
| SUB | (Rate as per item no 20.47.5 of SH : Water Supply)Rate as per item 18.30.5 | each | 2 | 428.65 | 857.30 |
- TOTAL
- 9,341.42
- Add 1 % Water charges on “W-A”
- +84.84
- TOTAL
- 9,426.26
- Add GST on “X-A” (multiplying factor 0.2127)
- +1,822.62
- TOTAL
- 11,248.88
- Add 15% CPOH on “Y-A”
- +1,558.74
- TOTAL
- 12,807.62
- Add Cess @ 1% on “Z-A”
- +119.50
- Cost for 10 dirt box stainer
- 12,927.12
- SAY
- ₹12,927.10
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1516
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1516. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.