Providing and fixing C.I. dirt box strainer for bulk type water meter with nuts, bolts, rubber insertions etc. complete conforming to IS : 2373

150 mm dia
Item number
18.61.3
Analysis basis
1 no
Priced inputs
4
Derived rate
₹9,433.10/ NO
D-01/RATE ANALYSISITEM 18.61.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.61.3 (Providing and fixing C.I. dirt box strainer for bulk type water meter with nuts, bolts, rubber insertions etc. complete conforming to IS : 2373: 150 mm dia) is derived from 4 priced inputs for 1 no and works out to ₹9,433.10 per no after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Providing flanged joints to double acting
  • air valves with bolts, nuts and rubber
  • insertions etc.
ANALYSIS OF RATES · ITEM 18.61.3DETAILS OF COST FOR 1 NO. DIRT BOX STAINER
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7424MATDirt box srainer 150 mmDirt box strainer 150 mmeach15,850.005,850.00
9977MATCarriage of dirt box strainerL.S.392.2788.53
9999MATLabour for laying dirt box strainerL.S.652.27147.55
SUB(Rate as per item No.18.30.4 Of SH:Water Supply)Rate as per item 18.30.4each2387.40774.80
BUILD-UP TO RATE
TOTAL
6,860.88
Add 1 % Water charges on “W-A”
+60.86
TOTAL
6,921.74
Add GST on “X-A” (multiplying factor 0.2127)
+1,307.45
TOTAL
8,229.19
Add 15% CPOH on “Y-A”
+1,118.16
TOTAL
9,347.35
Add Cess @ 1% on “Z-A”
+85.73
Cost for 1 dirt box stainer
9,433.08
SAY
₹9,433.10
D-02/SOURCEPRINTED PAGE 1516
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1516

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1516. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.