CPWD Analysis of Rates · Water Supply
Providing and fixing rectangular high density polyethylene water storage loft tank with cover, conforming to ISI : 12701, colour of opaque white or as approved by Engineer-incharge. The rate includes making necessary holes for inlet, outlet & over flow pipes. The base support i/c fittings & fixtures for tank shall be paid separately
- Item number
- 18.48A
- Analysis basis
- Details of cost for one no. tank of 500 litre
- Priced inputs
- 3
- Derived rate
- ₹11.00 / litre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.48A — Providing and fixing rectangular high density polyethylene water storage loft tank with cover, conforming to ISI : 12701, colour of opaque white or as approved by Engineer-incharge. The rate includes making necessary holes for inlet, outlet & over flow pipes. The base support i/c fittings & fixtures for tank shall be paid separately — is derived from 3 priced inputs for one no and works out to ₹11.00 per litre after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1649 | Polyethylene water storage tank with cover and suitable locking arrangementMaterial | per litre | 500 | 6.50 | 3,250.00 |
| 9977 | Carriage to siteMaterial | L.S. | 179.4 | 2.27 | 407.24 |
| 9999 | Placing at terraceMaterial | L.S. | 89.7 | 2.27 | 203.62 |
- TOTAL
- 3,860.86
- Add 1 % Water charges on “W”
- 38.61
- TOTAL
- 3,899.47
- Add GST on “X” (multiplying factor 0.2127)
- 829.42
- TOTAL
- 4,728.89
- Add 15% CPOH on “Y”
- 709.33
- TOTAL
- 5,438.22
- Add Cess @ 1% on “Z”
- 54.38
- Cost of 500 litre
- 5,492.60
- Cost of 1 litre
- 10.99
- Say
- 11.00
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1504. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.