Providing and placing on terrace (at all floor levels) polyethylene water storage tank, IS : 12701 marked, with cover and suitable locking arrangement and making necessary holes for inlet, outlet and overflow pipes but without fittings and the base support for tank
- Item number
- 18.48
- Analysis basis
- 500 litre
- Priced inputs
- 3
- Derived rate
- ₹11.00/ LITRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.48 (Providing and placing on terrace (at all floor levels) polyethylene water storage tank, IS : 12701 marked, with cover and suitable locking arrangement and making necessary holes for inlet, outlet and overflow pipes but without fittings and the base support for tank) is derived from 3 priced inputs for 500 litre and works out to ₹11.00 per litre after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1649 | MAT | Polyethylene water storage tank with cover and suitable locking arrangement | per litre | 500 | 6.50 | 3,250.00 |
| 9977 | MAT | Carriage to site | L.S. | 179.4 | 2.27 | 407.24 |
| 9999 | MAT | Placing at terrace | L.S. | 89.7 | 2.27 | 203.62 |
- TOTAL
- 3,860.86
- Add 1 % Water charges on “W”
- +38.61
- TOTAL
- 3,899.47
- Add GST on “X” (multiplying factor 0.2127)
- +829.42
- TOTAL
- 4,728.89
- Add 15% CPOH on “Y”
- +709.33
- TOTAL
- 5,438.22
- Add Cess @ 1% on “Z”
- +54.38
- Cost for 500 litre
- 5,492.60
- Cost of one litre
- 10.99
- SAY
- ₹11.00
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1503
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1503. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.