Skip to main content
R/DAR 2023

Providing and placing on terrace (at all floor levels) polyethylene water storage tank, IS : 12701 marked, with cover and suitable locking arrangement and making necessary holes for inlet, outlet and overflow pipes but without fittings and the base support for tank

Item number
18.48
Analysis basis
500 litre
Priced inputs
3
Derived rate
₹11.00/ LITRE
D-01/RATE ANALYSISITEM 18.48

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.48 (Providing and placing on terrace (at all floor levels) polyethylene water storage tank, IS : 12701 marked, with cover and suitable locking arrangement and making necessary holes for inlet, outlet and overflow pipes but without fittings and the base support for tank) is derived from 3 priced inputs for 500 litre and works out to ₹11.00 per litre after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 18.48DETAILS OF COST FOR 500 LITRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1649MATPolyethylene water storage tank with cover and suitable locking arrangementper litre5006.503,250.00
9977MATCarriage to siteL.S.179.42.27407.24
9999MATPlacing at terraceL.S.89.72.27203.62
BUILD-UP TO RATE
TOTAL
3,860.86
Add 1 % Water charges on “W”
+38.61
TOTAL
3,899.47
Add GST on “X” (multiplying factor 0.2127)
+829.42
TOTAL
4,728.89
Add 15% CPOH on “Y”
+709.33
TOTAL
5,438.22
Add Cess @ 1% on “Z”
+54.38
Cost for 500 litre
5,492.60
Cost of one litre
10.99
SAY
₹11.00
D-02/SOURCEPRINTED PAGE 1503
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1503

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1503. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.