CPWD Analysis of Rates · Water Supply

Providing and filling sand of grading zone V or coarser grade, allround the G.I. pipes in external work

50 mm diameter pipe

Item number
18.41.6
Analysis basis
Details of cost of sand filling alround
Priced inputs
1
Derived rate
173.25

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.41.6 Providing and filling sand of grading zone V or coarser grade, allround the G.I. pipes in external work : 50 mm diameter pipe — is derived from 1 priced inputs and works out to ₹173.25 after water charges, GST, CPOH and cess. The full build-up is below.

  • 50mm dia. pipe 10 metre long.
  • Width of sand filling = 300mm
  • Depth of sand filling
  • Under the pipe = 75mm+
  • Above the pipe = 150mm+
  • Max. external dia of pipe = 60.8mm
  • = 285.8 Say 286mm
  • Quantity of sand = 10x0.30x0.286 = 0.858
  • cum.+
  • (-)0.029cum.
  • = 0.829 Say 0.83 cum.
  • Less for pipe 3.142/4(60.8)²x10 =
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item Number 18.41.1A of SH:Water supplyRate as per item 18.41.1ASub-analysiscum0.832,087.301,732.46
TOTAL
1,732.46
Cost of 10 metre
1,732.46
Cost of one metre
173.25
Say
173.25

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1492. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.