Skip to main content
R/DAR 2023

Providing and filling sand of grading zone V or coarser grade, allround the G.I. pipes in external work

40 mm diameter pipe
Item number
18.41.5
Analysis basis
Details of cost of sand filling alround
Priced inputs
1
Derived rate
₹167.00
D-01/RATE ANALYSISITEM 18.41.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.41.5 (Providing and filling sand of grading zone V or coarser grade, allround the G.I. pipes in external work : 40 mm diameter pipe) is derived from 1 priced inputs and works out to ₹167.00 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 40mm dia. pipe 10 metre long.
  • Width of sand filling = 300mm
  • Depth of sand filling
  • Under the pipe = 75mm+
  • Above the pipe = 150mm+
  • Max. external dia of pipe = 48.8mm
  • = 273.8 Say 274mm
  • Quantity of sand = 10x0.30x0.274 = 0.82
  • cum.+
  • (-)0.014cum.
  • = 0.801 Say 0.80 cum.
  • Less for pipe 3.142/4(48.8)²x10 =
ANALYSIS OF RATES · ITEM 18.41.5DETAILS OF COST OF SAND FILLING ALROUND
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 18.41.1A of SH:Water supplyRate as per item 18.41.1Acum0.82,087.301,669.84
BUILD-UP TO RATE
TOTAL
1,669.84
Cost of 10 metre
1,669.84
Cost of one metre
166.98
SAY
₹167.00
D-02/SOURCEPRINTED PAGE 1492
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1492

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1492. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.