CPWD Analysis of Rates · Water Supply
Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes conforming to IS:15801, UV stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply, including all PP - R plain & brass threaded polypropylene random fittings and fixing the pipe with clamps at 1.00 m spacing. This includes testing of joints complete as per direction of Engineer-in-Charge. Internal Exposed on walls
PN - 16 Pipe, 25mm OD (SDR-7.4)
- Item number
- 18.4.2
- Analysis basis
- Details of cost for 10 metre
- Priced inputs
- 5
- Derived rate
- ₹318.35 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.4.2 — Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes conforming to IS:15801, UV stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply, including all PP - R plain & brass threaded polypropylene random fittings and fixing the pipe with clamps at 1.00 m spacing. This includes testing of joints complete as per direction of Engineer-in-Charge. Internal Exposed on walls PN - 16 Pipe, 25mm OD (SDR-7.4) — is derived from 5 priced inputs for 10 metre and works out to ₹318.35 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- MATERIAL:
- LABOUR:
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8627 | Poly propyleneRandom - Co - Polymer (PPR) pipes PN-16 (SDR 7.4) - 25 mm Outer diaPoly propylene- Random - Co - Polymer (PPR) pipes PN-16 (SDR 7.4) - 25 mm Outer diaMaterial | metre | 10 | 50.00 | 500.00 |
| 9999 | Cement,Sand and gritMaterial | L.S. | 2.73 | 2.27 | 6.20 |
| 0116 | Fitter (grade 1)Labour | day | 0.33 | 897.00 | 296.01 |
| 0117 | Assistant Fitter or 2nd class FitterLabour | day | 0.98 | 816.00 | 799.68 |
| 0114 | BeldarLabour | day | 0.66 | 736.00 | 485.76 |
- Add 30% for fittings, clamps and wastage etc. on P, 30xP/100
- 150.00
- TOTAL
- 2,237.65
- Add 1 % Water charges on “W”
- 22.38
- TOTAL
- 2,260.03
- Add GST on “X” (multiplying factor 0.2127)
- 480.71
- TOTAL
- 2,740.74
- Add 15% CPOH on “Y”
- 411.11
- TOTAL
- 3,151.85
- Add Cess @ 1% on “Z”
- 31.52
- Cost of 10 metre
- 3,183.37
- Cost of 1 metre
- 318.34
- Say
- 318.35
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1404. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works