Providing and fixing C.I. sluice valves (with cap) complete with bolts, nuts, rubber insertions etc. (the tail pieces if required will be paid separately) : 300 mm diameter
- Item number
- 18.31.6.1
- Analysis basis
- 10 sluice
- Priced inputs
- 3
- Derived rate
- ₹27,059.30/ VALVE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.31.6.1 (Providing and fixing C.I. sluice valves (with cap) complete with bolts, nuts, rubber insertions etc. (the tail pieces if required will be paid separately) : 300 mm diameter Class I) is derived from 3 priced inputs for 10 sluice and works out to ₹27,059.30 per valve after water charges, GST, CPOH and cess. The full build-up is below.
- Carriage of sluice valves
- wt. = 242.4x10=2424kg = 2.424t. say
- 2.42t
- Providing flanged joints to sluice valves
- with bolts, nuts and rubber insertion etc.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1945 | MAT | C.I.sluice valve (with caps) class I : 300 mm diaC.I. sluice valve (with caps) class I: 300 mm dia | each | 10 | 17,050.00 | 1,70,500.00 |
| SUB | (Rate as per item No. 18.24 Of SH: Water Supply)Rate as per item 18.24 | quintal | 24.24 | 661.85 | 16,043.24 | |
| SUB | (Rate as per item No.18.30.7 Of SH: Water Supply)Rate as per item 18.30.7 | each | 20 | 599.50 | 11,990.00 |
- TOTAL
- 1,98,533.24
- Add 1 % Water charges on “W-A”
- +1,705.00
- TOTAL
- 2,00,238.24
- Add GST on “X-A” (multiplying factor 0.2127)
- +36,628.00
- TOTAL
- 2,36,866.24
- Add 15% CPOH on “Y-A”
- +31,324.95
- TOTAL
- 2,68,191.19
- Add Cess @ 1% on “Z-A”
- +2,401.58
- Cost of 10 valves
- 2,70,592.77
- Cost of 1 valve
- 27,059.28
- SAY
- ₹27,059.30
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1472
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1472. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.