Providing and fixing Polyethelene-AluminiumPolyethelene PE-AL-PE Composite Pressure Pipes conforming to IS - 15450, U.V. stabilized with carbon black having thermal stability for hot & cold water supply, capable to withstand temperature up to 80°C, including all special fittings of composite material (engineering plastic blend and brass inserts wherever required) e.g. elbows, tees, reducers, couplers & connectors etc., with trenching, refilling and testing of joints complete as per direction of the engineer in charge. External work

4050 (50 mm OD ) pipe
Item number
18.3.6
Analysis basis
10 metre
Priced inputs
5
Derived rate
₹799.80/ METRE
D-01/RATE ANALYSISITEM 18.3.6

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.3.6 (Providing and fixing Polyethelene-AluminiumPolyethelene PE-AL-PE Composite Pressure Pipes conforming to IS - 15450, U.V. stabilized with carbon black having thermal stability for hot & cold water supply, capable to withstand temperature up to 80°C, including all special fittings of composite material (engineering plastic blend and brass inserts wherever required) e.g. elbows, tees, reducers, couplers & connectors etc., with trenching, refilling and testing of joints complete as per direction of the engineer in charge. External work 4050 (50 mm OD ) pipe) is derived from 5 priced inputs for 10 metre and works out to ₹799.80 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 30 x P / 100
  • Trenching and refilling etc.
ANALYSIS OF RATES · ITEM 18.3.6DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8305MAT4050 mm PE-AL-PE Composit pressure pipe4050 mm PE-AL-PE Composite pressure pipemetre10328.003,280.00
0116LABFitter (grade 1)day0.16897.00143.52
0114LABBeldarday0.33736.00242.88
0114LABBeldarday0.66736.00485.76
0115LABCoolieday0.66736.00485.76
BUILD-UP TO RATE
Add 30% for fittings and wastage etc. on (P)
+984.00
TOTAL
5,621.92
Add 1 % Water charges on “W”
+56.22
TOTAL
5,678.14
Add GST on “X” (multiplying factor 0.2127)
+1,207.74
TOTAL
6,885.88
Add 15% CPOH on “Y”
+1,032.88
TOTAL
7,918.76
Add Cess @ 1% on “Z”
+79.19
Cost of 10 metre
7,997.95
Cost of 1 metre
799.80
SAY
₹799.80
D-02/SOURCEPRINTED PAGE 1403
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1403

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1403. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.