Providing and fixing Polyethelene-AluminiumPolyethelene PE-AL-PE Composite Pressure Pipes conforming to IS - 15450, U.V. stabilized with carbon black having thermal stability for hot & cold water supply, capable to withstand temperature up to 80°C, including all special fittings of composite material (engineering plastic blend and brass inserts wherever required) e.g. elbows, tees, reducers, couplers & connectors etc., with trenching, refilling and testing of joints complete as per direction of the engineer in charge. External work
- Item number
- 18.3.6
- Analysis basis
- 10 metre
- Priced inputs
- 5
- Derived rate
- ₹799.80/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.3.6 (Providing and fixing Polyethelene-AluminiumPolyethelene PE-AL-PE Composite Pressure Pipes conforming to IS - 15450, U.V. stabilized with carbon black having thermal stability for hot & cold water supply, capable to withstand temperature up to 80°C, including all special fittings of composite material (engineering plastic blend and brass inserts wherever required) e.g. elbows, tees, reducers, couplers & connectors etc., with trenching, refilling and testing of joints complete as per direction of the engineer in charge. External work 4050 (50 mm OD ) pipe) is derived from 5 priced inputs for 10 metre and works out to ₹799.80 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- 30 x P / 100
- Trenching and refilling etc.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8305 | MAT | 4050 mm PE-AL-PE Composit pressure pipe4050 mm PE-AL-PE Composite pressure pipe | metre | 10 | 328.00 | 3,280.00 |
| 0116 | LAB | Fitter (grade 1) | day | 0.16 | 897.00 | 143.52 |
| 0114 | LAB | Beldar | day | 0.33 | 736.00 | 242.88 |
| 0114 | LAB | Beldar | day | 0.66 | 736.00 | 485.76 |
| 0115 | LAB | Coolie | day | 0.66 | 736.00 | 485.76 |
- Add 30% for fittings and wastage etc. on (P)
- +984.00
- TOTAL
- 5,621.92
- Add 1 % Water charges on “W”
- +56.22
- TOTAL
- 5,678.14
- Add GST on “X” (multiplying factor 0.2127)
- +1,207.74
- TOTAL
- 6,885.88
- Add 15% CPOH on “Y”
- +1,032.88
- TOTAL
- 7,918.76
- Add Cess @ 1% on “Z”
- +79.19
- Cost of 10 metre
- 7,997.95
- Cost of 1 metre
- 799.80
- SAY
- ₹799.80
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1403
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1403. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.