Providing and laying S&S C.I. standard specials such as tees, bends, collars, tapers, caps etc. (Heavy class)

Up to 300 mm dia
Item number
18.25.1
Analysis basis
1 quintal
Priced inputs
2
Derived rate
₹6,352.40/ QUINTAL
D-01/RATE ANALYSISITEM 18.25.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.25.1 (Providing and laying S&S C.I. standard specials such as tees, bends, collars, tapers, caps etc. (Heavy class): Up to 300 mm dia) is derived from 2 priced inputs for 1 quintal and works out to ₹6,352.40 per quintal after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 18.25.1DETAILS OF COST FOR 1 QUINTAL
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1464MATS & S.C.I.standard specials upto 300 mm dia (heavy class)S & S.C.I. standard specials upto 300 mm dia (heavy class)quintal14,000.004,000.00
SUBRate as per item No. 18.24 Of SH: Water SupplyRate as per item 18.24quintal1661.85661.85
BUILD-UP TO RATE
TOTAL
4,661.85
Add 1 % Water charges on “W-A”
+40.00
TOTAL
4,701.85
Add GST on “X-A” (multiplying factor 0.2127)
+859.31
TOTAL
5,561.16
Add 15% CPOH on “Y-A”
+734.90
TOTAL
6,296.06
Add Cess @ 1% on “Z-A”
+56.34
Cost of one quintal
6,352.40
SAY
₹6,352.40
D-02/SOURCEPRINTED PAGE 1448
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1448

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1448. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.