CPWD Analysis of Rates · Water Supply
Laying in position centrifugally cast (spun) iron S&S or flanged pipes (excluding cost of pipe)
- Item number
- 18.23
- Analysis basis
- Details of cost for 5.14 quintal
- Priced inputs
- 4
- Derived rate
- ₹361.65 / quintal
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.23 — Laying in position centrifugally cast (spun) iron S&S or flanged pipes (excluding cost of pipe) — is derived from 4 priced inputs for 5.14 quintal and works out to ₹361.65 per quintal after water charges, GST, CPOH and cess. The full build-up is below.
- 10 m of 200 mm dia C.I. pipe class ‘A’
- Weight = (2x257) = 514kg = 5.14 quintal
- LABOUR for laying pipe
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0116 | Fitter (grade 1)Labour | day | 0.17 | 897.00 | 152.49 |
| 0117 | Assistant Fitter or 2nd class FitterLabour | day | 0.17 | 816.00 | 138.72 |
| 0114 | BeldarLabour | day | 1.33 | 736.00 | 978.88 |
| 9999 | SundriesMaterial | L.S. | 16.12 | 2.27 | 36.59 |
- TOTAL
- 1,306.68
- Add 1 % Water charges on “W”
- 13.07
- TOTAL
- 1,319.75
- Add GST on “X” (multiplying factor 0.2127)
- 280.71
- TOTAL
- 1,600.46
- Add 15% CPOH on “Y”
- 240.07
- TOTAL
- 1,840.53
- Add Cess @ 1% on “Z”
- 18.41
- Cost of 5.14 quintal
- 1,858.94
- Cost of one quintal
- 361.66
- Say
- 361.65
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1448. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.