CPWD Analysis of Rates · Water Supply

Providing and fixing G.I. Pipes complete with G.I. fittings and clamps, including making good the walls etc. concealed pipe, including painting with anti corrosive bitumastic paint, cutting chases and making good the wall

20 mm dia nominal bore

Item number
18.11.2
Analysis basis
Details of cost for 10 metre
Priced inputs
7
Derived rate
635.20 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.11.2 Providing and fixing G.I. Pipes complete with G.I. fittings and clamps, including making good the walls etc. concealed pipe, including painting with anti corrosive bitumastic paint, cutting chases and making good the wall : 20 mm dia nominal bore — is derived from 7 priced inputs for 10 metre and works out to ₹635.20 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Weight for carriage = pipe weight + 15%
  • for fiitings = 1.15 * 15.90= 18 kg = 0.018
  • tonne
  • Painting G.I. pipe with anti-corrosive
  • bitumastic paint two or more coats
  • Making chases upto 7.5x7.5cm in walls
  • and making good the same
CodeInputUnitQuantityRate (INR)Amount (INR)
1546G.I. pipes 20 mm diaMaterialmetre11.5139.001,598.50
9999White lead, hemp, oil etc.MaterialL.S.8.062.2718.30
(Rate same as per item no. 18.40.2 Of SH Water Supply)Rate as per item 18.40.2Sub-analysismetre1014.45144.50
Rate as per item no. 18.78 Of SH Water SupplyRate as per item 18.78Sub-analysismetre10202.902,029.00
0116Fitter (grade 1)Labourday0.33897.00296.01
0117Assistant Fitter or 2nd class FitterLabourday0.66816.00538.56
0114BeldarLabourday0.66736.00485.76
TOTAL
5,110.63
Add 1 % Water charges on “W-A”
29.37
TOTAL
5,140.00
Add GST on “X-A” (multiplying factor 0.2127)
630.97
TOTAL
5,770.97
Add 15% CPOH on “Y-A”
539.62
TOTAL
6,310.59
Add Cess @ 1% on “Z-A”
41.37
Cost of 10 metre
6,351.96
Cost of 1 metre
635.20
Say
635.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1430. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.