CPWD Analysis of Rates · Water Supply
Providing and fixing G.I. Pipes complete with G.I. fittings and clamps, including making good the walls etc. concealed pipe, including painting with anti corrosive bitumastic paint, cutting chases and making good the wall
15 mm dia nominal bore
- Item number
- 18.11.1
- Analysis basis
- Details of cost for 10 metre
- Priced inputs
- 7
- Derived rate
- ₹580.45 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.11.1 — Providing and fixing G.I. Pipes complete with G.I. fittings and clamps, including making good the walls etc. concealed pipe, including painting with anti corrosive bitumastic paint, cutting chases and making good the wall : 15 mm dia nominal bore — is derived from 7 priced inputs for 10 metre and works out to ₹580.45 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Weight for carriage = pipe weight + 15%
- for fiitings = 1.15 * 12.30 = 14 kg = 0.014
- tonne
- Painting G.I. pipe with anti-corrosive
- bitumastic paint two or more coats
- Making chases upto 7.5x7.5cm in walls
- and making good the same
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1545 | G.I. pipes 15 mm diaMaterial | metre | 11.5 | 107.00 | 1,230.50 |
| 9999 | White lead, hemp, oil etc.Material | L.S. | 8.06 | 2.27 | 18.30 |
| (Rate same as per item no. 18.40.1)Rate as per item 18.40.1Sub-analysis | metre | 10 | 12.05 | 120.50 | |
| Rate as per item no. 18.78 Of SH Water SupplyRate as per item 18.78Sub-analysis | metre | 10 | 202.90 | 2,029.00 | |
| 0116 | Fitter (grade 1)Labour | day | 0.33 | 897.00 | 296.01 |
| 0117 | Assistant Fitter or 2nd class FitterLabour | day | 0.66 | 816.00 | 538.56 |
| 0114 | BeldarLabour | day | 0.66 | 736.00 | 485.76 |
- TOTAL
- 4,718.63
- Add 1 % Water charges on “W-A”
- 25.69
- TOTAL
- 4,744.32
- Add GST on “X-A” (multiplying factor 0.2127)
- 551.92
- TOTAL
- 5,296.24
- Add 15% CPOH on “Y-A”
- 472.01
- TOTAL
- 5,768.25
- Add Cess @ 1% on “Z-A”
- 36.19
- Cost of 10 metre
- 5,804.44
- Cost of 1 metre
- 580.44
- Say
- 580.45
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1429. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.