Providing and laying water proofing treatment in sunken portion of WCs, bathroom etc., by applying cement slurry mixed with water proofing cement compound consisting of applying : (a) First layer of slurry of cement @ 0.488 kg/sqm mixed with water proofing cement compound @ 0.253 kg/ sqm. This layer will be allowed to air cure for 4 hours. (b) Second layer of slurry of cement @ 0.242 kg/sqm mixed with water proofing cement compound @ 0.126 kg/sqm. This layer will be allowed to air cure for 4 hours followed with water curing for 48 hours. The rate includes preparation of surface, treatment and sealing of all joints, corners, junctions of pipes and masonry with polymer mixed slurry

Item number
22.5
Analysis basis
10 sqm
Priced inputs
6
Derived rate
₹617.05/ SQM
D-01/RATE ANALYSISITEM 22.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 22.5 (Providing and laying water proofing treatment in sunken portion of WCs, bathroom etc., by applying cement slurry mixed with water proofing cement compound consisting of applying : (a) First layer of slurry of cement @ 0.488 kg/sqm mixed with water proofing cement compound @ 0.253 kg/ sqm. This layer will be allowed to air cure for 4 hours. (b) Second layer of slurry of cement @ 0.242 kg/sqm mixed with water proofing cement compound @ 0.126 kg/sqm. This layer will be allowed to air cure for 4 hours followed with water curing for 48 hours. The rate includes preparation of surface, treatment and sealing of all joints, corners, junctions of pipes and masonry with polymer mixed slurry) is derived from 6 priced inputs for 10 sqm and works out to ₹617.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement 10x(0.488+0.242) = 7.30 kg
  • Sealing fillets 10x0.5 kg / sqm = 5.00 kg
  • Total = 12.30 kg = 0.012 tonne
  • Bonding material 1.6 kgx30x2 = 96 kg
  • Bitumen (blown/residual type) 10x(0.25+0.126)
  • = 3.79 kg
  • Sealing fillets 10x0.10 kg / sqm = 1.00 kg
  • Wastage @ 5% on 4.79 kg = 0.24 kg
  • Total = 5.03 kg Say 5.00 kg
ANALYSIS OF RATES · ITEM 22.5DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0367MATPortland Cement (OPC-43 grade)tonne0.0125,156.0061.87
8501MATPolymer modified cementation coatingkilogram5170.00850.00
0155LABMason (average)day2857.001,714.00
0114LABBeldarday2736.001,472.00
0101LABBhistiday0.25816.00204.00
9999MATSundries, brushes etcL.S.15.62.2735.41
BUILD-UP TO RATE
TOTAL
4,337.28
Add 1 % Water charges on “W”
+43.37
TOTAL
4,380.65
Add GST on “X” (multiplying factor 0.2127)
+931.76
TOTAL
5,312.41
Add 15% CPOH on “Y”
+796.86
TOTAL
6,109.27
Add Cess @ 1% on “Z”
+61.09
Cost for 10 sqm
6,170.36
Cost for 1 sqm
617.04
SAY
₹617.05
D-02/SOURCEPRINTED PAGE 1849
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1849

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1849. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER PROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.